CS92 Energy Code Feasibility Study in Brockton, Massachusetts

Energy code feasibility study for a 41-unit high-rise in Massachusetts. Compares multiple design paths. Recommended: PROPOSED (All-Electric). View full study.

Study Type
Energy Code Feasibility Study
State
Massachusetts
Units
41
Building Type
high-rise
Fuel Type
All-Electric
Recommended Path
PROPOSED (All-Electric)

Goal

To find the most cost-effective compliance path, this report isolates energy code related costs from total construction. We use real bid data from vendors & clients to create a reliable framework for aligning incentives and design, with all recommendations confirmed by detailed energy modeling.

Project

  • Brockton, MA 02301
  • 1 Building | 41 Units | 37,782 SF Conditioned
  • New Construction | 6-story high-rise multifamily (x1)
  • All-Electric | 2021 IECC with MA Amendments (Stretch Code) | HERS ≤ 45 | ENERGY STAR MFNC v1.2

Overview

Read This: This report compares different ways you can build the project and meet energy code, looking at both cost and incentives, with the ultimate goal as finding the most affordable path.

  • The overview outlines the key differences between each of the paths we show in this report and why we recommend the one we picked over the others.
  • The recommended design section is where we share the requirements and incentives for the path we think is best based on affordability.
  • The path comparison section shows the detailed requirements and incentives for each path we compared, basically showing our work if you want to dig in.

Product Recs: All product recommendations are recommendations only and can be substituted with any equivalent or better match.

Path Summaries

Both paths are all-electric new construction under the Massachusetts Stretch Code HERS 45 ceiling, both certify for ENERGY STAR Multifamily New Construction, and PROPOSED costs less before the incentive and after it.

PROPOSED (All-Electric): Recommended

The goal of this path was to show an all-electric new-construction design under the Massachusetts Stretch Code HERS 45 ceiling that certifies for ENERGY STAR Multifamily New Construction, because it meets that ceiling at a lower cost. The estimated energy-related cost is $59.32/sf with a $1.90/sf incentive, for a net of $58.46/sf. The main advantage of this path is the lower construction cost, before the incentive and after it, and a simpler floor line, because floors 1 and 2 are steel and floors 3 through 5 are wood, and those floors use the same continuous insulation, so the floor bands do not need an insulation transition. It meets the Massachusetts Stretch Code and certifies for ENERGY STAR Multifamily New Construction, with the air barrier on the sheathing and the roof air barrier on the deck, and it keeps off costly upgrades like the extra attic insulation and the lower-U windows.

HPWH (All-Electric): Alternative

The goal of this path was to show an all-electric new-construction package under the same Massachusetts Stretch Code HERS 45 ceiling and the same ENERGY STAR Multifamily New Construction certification, with more attic insulation and lower-U windows than PROPOSED. The estimated energy-related cost is $61.37/sf with a $1.90/sf incentive, for a net of $60.64/sf. The main advantage of this path is there is none, since the net is $2.18/sf more than PROPOSED, the incentive is the same, and the steel floors and the wood floors do not share one continuous insulation, so the floor bands need an insulation transition. It meets the Massachusetts Stretch Code and certifies for ENERGY STAR Multifamily New Construction, and the extra cost pays for the lower-U windows and an added attic insulation layer.

What Changes Between Paths

Item

HPWH

PROPOSED (Recommended)

Exterior Walls

Floors 1-2: ≥ R-21 cavity insulation (2x6 steel @ 16" o.c.) with ≥ R-5 continuous exterior insulation. Floors 3-5: ≥ R-23 cavity insulation (2x6 wood @ 16" o.c.), no continuous insulation. Suitable alternative for the steel wall: ≥ R-13 cavity plus ≥ R-10 continuous.

Floors 1-2: ≥ R-21 cavity insulation (2x6 steel @ 16" o.c., 5.5 in) with ≥ R-3.8 polyiso continuous exterior insulation (1 in). Floors 3-5: ≥ R-21 cavity insulation (2x6 wood @ 16" o.c., 5.5 in) with ≥ R-3.8 polyiso continuous exterior insulation (1 in). Steel and wood share the same R-3.8 continuous insulation, so there is no insulation transition between floors. Suitable alternative for the steel wall: ≥ R-13 cavity plus ≥ R-10 continuous.

Roof

Sealed attic: ≥ R-19 insulation + ≥ R-30 continuous insulation.

Sealed attic: ≥ R-30 continuous insulation.

Windows & Glass Doors

High performance, U ≤ 0.25 / SHGC ≤ 0.25.

High performance, U ≤ 0.27 / SHGC ≤ 0.30.

Cost $/sf

$61.37

$59.32

Incentive $/sf

$1.90

$1.90

Net $/sf

$60.64

$58.46

Permit / Certificate of Occupancy Requirements

Permit / Certificate of Occupancy Requirements

Multifamily Buildings

Multifamily Buildings

Code Path

  • HERS: Brockton is a Stretch Code town. The buildings are 6-story Group R under 225 CMR 23, and the dwelling units comply by per-unit HERS under section C407.4. The all-electric Stretch ceiling is HERS ≤ 45 (Table C407.4, new construction column). Section C407.4.1 requires the building to meet ENERGY STAR Multifamily New Construction.

Permit Requirements

  • HERS: With the building permit application, per 225 CMR 23 section C407.4.2.1: the proposed HERS Index on the title page and plans, the rater's name, the software name and version, all modeled inputs, and a certificate showing each dwelling unit type at or below the Table C407.4 ceiling, with the component specifications behind it (insulation R-values and U-factors, assumed duct and envelope leakage, and heating, cooling, ventilation, and water-heating types and efficiencies), on the worst-case orientation where no site-specific report is produced. ENERGY STAR Multifamily New Construction design review by the rater is part of that package (C407.4.1).

Certificate of Occupancy Requirements

  • HERS: Before certificate of occupancy, per 225 CMR 23 section C407.4.2.2: the final HERS Index on the title page and plans, a confirmed as-built HERS certificate for each rated unit with the duct and envelope air-leakage test results and the installed equipment efficiencies, and documentation that each unit meets ENERGY STAR Multifamily New Construction (item 7). C405.13 EV-ready and Appendix CB solar-ready compliance close out with it (item 9). A certified HERS rater verifies the package (C407.4.3). Air-leakage testing follows ANSI/RESNET/ICC 380, and RESNET sampling is permitted because each building has more than 8 units (C402.5.2.2).

Recommended Design

This section outlines the design requirements, product recommendations, and incentives for the design that we believe will be the most affordable path to meeting energy code.

Recommended Design - Incentives

Incentives Available: $71,750 - $133,250

  • MassSave Multifamily Program Energy Star Tier ($71,750) (Program Breakdown): You get this rebate for having your building(s) certified for the Energy Star MFNC v1.2 program. This requires pre-approval via an application to be submitted before construction starts. This rebate comes in the form of a check within 4 months of certification documentation being provided to MassSave, typically this is 4 months after construction is complete.
  • DOER Alternative Energy Credits ($0 - $61,500) (Program Breakdown): This rebate is received for installing APS eligible air source heat pumps (click here for the list). There is an extensive process to get this incentive. It comes in the form of a check approximately 6-12 months after the heat pumps are installed and fully operational.
    • IMPORTANT: Although an estimate is provided, this incentive can vary widely typically between $300-1,500 per heat pump. It's based on expected kWh usage of the system as well as the market value of the alternative energy credits when sold.
    • Risks: Massachusetts is rewriting this program right now. The House bill would stop the state from accepting new applications on January 1, 2028, the Senate version leaves heat pumps out of that cutoff, and the two are in conference. The application needs the equipment installed and operating, so a project that will not reach that point before the deadline should treat this as upside rather than a budgeted line.

HVAC Design Loads

Plymouth County, MA · heating 9.0°F/70.0°F · cooling 88.0°F/75.0°F · all values kBtuh

Design heat loss · components

Unit type

Walls & rim joists

Roof / ceiling

Slab, floors & below grade

Windows & doors

Infiltration

Ventilation

Design heat loss

Design heat loss at selection

1-Bedroom

1.2

1.3

0.0

2.1

3.3

1.8

9.8 @ 9°F

10.4 @ 5°F

2-Bedroom

3.0

1.1

0.0

3.5

4.9

2.4

14.9 @ 9°F

15.9 @ 5°F

3-Bedroom

4.3

1.3

0.0

4.2

5.6

2.4

17.9 @ 9°F

19.1 @ 5°F

Design heat gain · components

Unit type

Solar through glazing

Envelope conduction

Internal gains

Infiltration & ventilation

Latent

Total heat gain

Sensible heat ratio

1-Bedroom

2.9

1.1

2.1

1.7

2.8

10.6

0.73

2-Bedroom

4.0

1.7

2.3

2.3

3.9

14.2

0.72

3-Bedroom

3.6

2.2

2.5

2.5

4.4

15.1

0.71

Selection

Unit type

Cooling Capacity

Minimum Heating Capacity

1-Bedroom

9.5 to 20.0 kBtuh rated

≥ 10.4 kBtuh @ 5°F

2-Bedroom

12.8 to 20.0 kBtuh rated

≥ 15.9 kBtuh @ 5°F

3-Bedroom

13.6 to 19.6 kBtuh rated

≥ 19.1 kBtuh @ 5°F

ENERGY STAR Total UA

Item

Detail

Climate zone

IECC 5A (2021 IECC map)

Program

ENERGY STAR MFNC National v1.2 Rev. 05

Rule

Design Review Item 2.1 / Fn 11-12; Proposed UA ≤ Reference UA

Code reference

Exhibit 1 Table 1 (2021 IECC CZ); Design Review Item 2.1 / Fn 11-12

Version basis

explicit program key (v1.2)

Note

Code minimum for this permit is v1.1; v1.2 used for explicit program key (v1.2). Confirm certification path matches the incentive or AHJ requirement. Proposed U for walls, roof, windows, doors is the area-weighted Ekotrope assembly U. Any component without an Ekotrope U keeps the spec lookup.

Assembly

Proposed spec

Walls

Floors 1-2: ≥ R-21 cavity insulation (2x6 steel @ 16" o.c., 5.5 in) with ≥ R-3.8 polyiso continuous exterior insulation (1 in). Floors 3-5: ≥ R-21 cavity insulation (2x6 wood @ 16" o.c., 5.5 in) with ≥ R-3.8 polyiso continuous exterior insulation (1 in). Steel and wood share the same R-3.8 continuous insulation, so there is no insulation transition between floors. Suitable alternative for the steel wall: ≥ R-13 cavity plus ≥ R-10 continuous.

Roof

Sealed attic: ≥ R-30 continuous insulation.

Windows

High performance, U ≤ 0.27 / SHGC ≤ 0.30.

Doors

Opaque door, U ≤ 0.20 (R-5.0).

Slab

N/A

Envelope Takeoffs

Building

Opaque walls (sf)

Roof (sf)

Windows (sf)

69

27,437

7,761

6,200

Component UA

Component

Quantity

Proposed U or F

Proposed UA

Reference U or F

Reference UA

Opaque exterior walls

27,437 sf

0.049

1,340

0.045

1,235

Roof / ceiling

7,761 sf

0.030

231

0.024

186

Windows & glass doors

6,200 sf

0.270

1,674

0.270

1,674

Total UA

Building

Proposed UA

Reference UA

% of reference

Result

69

3,245

3,095

104.8%

FAIL

Site total

3,245

3,095

104.8%

FAIL

Recommended Design - Units

Item

Detailed Specifications

Exterior Walls

Floors 1-2: ≥ R-21 cavity insulation (2x6 steel @ 16" o.c., 5.5 in) with ≥ R-3.8 polyiso continuous exterior insulation (1 in). Floors 3-5: ≥ R-21 cavity insulation (2x6 wood @ 16" o.c., 5.5 in) with ≥ R-3.8 polyiso continuous exterior insulation (1 in). Steel and wood share the same R-3.8 continuous insulation, so there is no insulation transition between floors. Suitable alternative for the steel wall: ≥ R-13 cavity plus ≥ R-10 continuous. (Product Rec).

Below Grade Walls

N/A

Corridor Walls

N/A

Slab

N/A

Floor Over Unconditioned Space

N/A

Floor Over Garage

N/A

Floor Over Podium

N/A

Rim Joists

≥ R-21 rim/band insulation at floor transitions.

Roof

Sealed attic: ≥ R-30 continuous insulation.

Windows & Glass Doors

High performance, U ≤ 0.27 / SHGC ≤ 0.30. (Product Rec).

Doors

Opaque door, U ≤ 0.20 (R-5.0).

Air Sealing

≤ 0.27 CFM50 per sqft of shell; tested. (Air Sealing Protocol)

HVAC

Ducted air-source heat pump (as modeled); SEER2 ≥ 17.5; HSPF2 ≥ 10.5. See HVAC Design Loads. (Product Rec).

Ductwork

Supply and return ducts in conditioned space insulated to code minimum.

Duct Sealing

≤ greater of 80 CFM25 or 8 CFM25 per 100 sqft of conditioned floor area; tested at final. (Duct Sealing Protocol)

HVAC Grading

Fan Flow Test: Grade II
Watt Draw Test: Grade II
Refrigerant Charge: Grade I (weigh-in method)
HVAC installer must provide photo of the digital refrigerant scale showing the amount charged, with the tank on the scale and hoses connected to the outdoor unit, along with a photo of the outdoor unit's data plate.
If the non-invasive procedure in ANSI / RESNET / ACCA 310 is not permitted to be used during the final inspection of a unit (i.e., due to the equipment type or to outdoor air temperatures that do not meet the requirements of the non-invasive method), then the unit is permitted to be certified with a default refrigerant charge designation of Grade III. Note that in these circumstances, the weigh-in method procedure in ANSI / RESNET / ACCA 310 may still be used to pursue a Grade I designation.

Mechanical Ventilation

In-unit ERV (Product Rec).
1-bedroom: 70 CFM, ≥ 87% ASRE
2-bedroom: 90 CFM, ≥ 81% ASRE
3-bedroom: 90 CFM, ≥ 81% ASRE

Local Mechanical Exhaust

Bathroom(s): at least 50 CFM intermittent and up to 3.0 sones, or at least 20 CFM continuous and up to 2.0 sones.
Kitchen(s): at least 100 CFM intermittent and up to 3.0 sones, or continuous at 5 ACH.
Both: exhaust directly outdoors with ENERGY STAR certified fans. A balanced ERV or HRV serving the space may satisfy this requirement.

Thermostats

Programmable thermostat (as modeled).

DHW

1-Bedroom: Heat pump water heater (HPWH) (as modeled); UEF ≥ 3.88; 40 gal (Product Rec).
2-Bedroom: Heat pump water heater (HPWH) (as modeled); UEF ≥ 3.88; 50 gal
3-Bedroom: Heat pump water heater (HPWH) (as modeled); UEF ≥ 3.88; 65 gal

DHW Piping

Supply piping insulated to ≥ R-3.

Water Fixtures

WaterSense certified (Lavatory ≤ 1.2 GPM; Shower ≤ 2.0 GPM; Kitchen ≤ 2.2 GPM).

Refrigerator

≤ 600 kWh/yr; electric. (Product Rec).

Dishwasher

≤ 269 kWh/yr; electric. (Product Rec).

Clothes Washer

IMEF ≥ 2.06; IWF ≤ 4.2; ≤ 152 kWh/yr; electric. (Product Rec).

Clothes Dryer

Heat pump dryer; ventless; CEF ≥ 6. (Product Rec).

Stove / Oven

Electric range. (Product Rec).

Lighting

≥ 100% high-efficacy (LED).

Solar Ready

N/A

EV Ready

At least 20% of parking spaces wired EV-ready (40-amp Level II; shared circuits with load management allowed).

HPWH Ready

N/A

Paperwork & Modeling

ENERGY STAR energy model to the target (per-unit HERS or whole-building ASHRAE path), the ENERGY STAR design-review checklist and multifamily workbook, and an HVAC design report.

Testing & Verification

ENERGY STAR field verification: pre-drywall and final inspections, unit air-tightness (blower door), duct-leakage, ventilation and exhaust airflow, and HVAC functional testing.

Recommended Design - Common Areas

Item

Common Areas (Residential Building)

Exterior Walls

Floors 1-2: steel studs, ≥ R-21 cavity plus ≥ R-3.8 continuous.
Alternative for the steel wall: ≥ R-13 cavity plus ≥ R-10 continuous.
Floors 3-5: wood studs, ≥ R-21 cavity plus ≥ R-3.8 continuous.
Both bands use the same R-3.8 continuous insulation, so there is no insulation transition.

Below Grade Walls

Basement foundation wall.
≥ R-15 continuous.
Or ≥ R-19 cavity.
Or ≥ R-13 cavity plus ≥ R-5 continuous.
From the top of the wall to 10 ft below grade or the basement floor, whichever is less.

Corridor Walls

N/A

Slab

Basement slab less than 10 ft below grade.
≥ R-10 continuous at the perimeter, extending 4 ft or 24 in below grade, whichever is greater.

Floor Over Unconditioned Space

≥ R-30 cavity.
Or ≥ R-19 cavity plus ≥ R-5 continuous.
Or ≥ R-13 cavity plus ≥ R-17 continuous.

Floor Over Garage

N/A

Floor Over Podium

N/A

Rim Joists

≥ R-21 rim/band insulation at floor transitions.

Roof

Sealed attic: ≥ R-19 insulation + ≥ R-30 continuous insulation.

Windows & Glass Doors

Fixed U ≤ 0.34.
Operable U ≤ 0.43.
SHGC ≤ 0.40.
ENERGY STAR MFNC Multifamily Reference Design, common-space windows, climate zone 5.

Doors

Glazed entrance U ≤ 0.60, SHGC ≤ 0.40.
ENERGY STAR MFNC Multifamily Reference Design, common-space glazed entrance doors, climate zone 5.

Air Sealing

Continuous air barrier for these spaces.
Hallways, stairwells, and enclosed common spaces not greater than 1,500 sqft, verified by inspection.
225 CMR 23 C402.5.2.2

HVAC

Ducted split HP: SEER2 15.2 / HSPF2 7.8.
Ductless: 16 / 8.2.
Packaged: 15.2 / 7.7.
PTAC/PTHP/room AC certified to ENERGY STAR.
Manual J/S sizing.

Ductwork

Ducts and air handlers serving these spaces are in conditioned space.
A supply or return duct outside conditioned space is insulated to at least R-6.
ENERGY STAR MFNC Exhibit 1; HVAC Design Supplement for Common Spaces, Item 5.3.

Duct Sealing

Supply, return, and exhaust ducts and plenums serving these spaces are sealed at transverse joints, longitudinal seams, and duct wall penetrations.
ENERGY STAR MFNC HVAC Design Supplement for Common Spaces, Item 5.4.

HVAC Grading

N/A

Mechanical Ventilation

Outdoor air to the community space and the hallways, at the ASHRAE 62.1 Section 6 rate for that space.
The design rate is not more than 50 percent above the ASHRAE 62.1-2013 minimum.
The system runs automatically.
ENERGY STAR MFNC HVAC Design Supplement for Common Spaces, Items 2.1 and 2.12.

Local Mechanical Exhaust

N/A

Thermostats

Programmable thermostat.
ENERGY STAR MFNC Multifamily Reference Design, Exhibit 1.

DHW

electric tank or instant hot water heater, UEF ≥ 0.93

DHW Piping

R-3 (1.5 in. and smaller); R-4 (larger)

Water Fixtures

WaterSense
Lav 1.5 GPM
Toilet 1.28 GPF
Urinal 0.5 GPF

Refrigerator

N/A

Dishwasher

N/A

Clothes Washer

N/A

Clothes Dryer

N/A

Stove / Oven

N/A

Lighting

100% LED.
Community space 0.59 W/sqft.
Hallways 0.41 W/sqft.
Basement storage 0.38 W/sqft.
Maintenance and electrical rooms 0.43 W/sqft.
IECC 2021 Table C405.3.2(2)

Lighting Controls

Occupant sensors in the community space, hallways, and basement storage.
Hallway sensors reduce lighting to not more than 50 percent of full power within 20 minutes after the corridor is empty.
Interior exit stairways are exempt from lighting controls.
Daylight-responsive controls where general lighting exceeds 100 W in a primary sidelit zone, 300 W in a sidelit zone, or 100 W in a toplit zone.
IECC 2021 C405.2.1.4
225 CMR 23 C405.2.4

Solar Ready

N/A

EV Ready

20% of parking spaces EV-ready.
40-amp dedicated branch circuit, or a larger branch circuit with automatic load management.
Wiring suitable for 6.6 kW or higher Level II EVSE, run to within 6 feet of the space.
One Level II space may be replaced by three Level I spaces wired for 20-amp, 120-volt EVSE.
225 CMR 23 C405.13 and Table C405.13

HPWH Ready

N/A

Electric Readiness

N/A

Vestibules

Self-closing vestibule at public building entrances; exempt if building under 3,000 sqft, or for employee-only/mechanical room doors, dwelling unit doors, revolving doors, or air curtains.

Efficiency Credits

N/A

Paperwork & Modeling

HERS index certificate at permit and at certificate of occupancy.
ENERGY STAR Multifamily New Construction workbook, design-review checklist, field checklist, and common-space HVAC supplement.
EV-ready space locations, wiring diagram, and load calculations.
225 CMR 23 C407.4.2 and C405.13.2

Testing & Verification

Hallways, stairwells, and enclosed common spaces not greater than 1,500 sqft verified by inspection of the continuous air barrier.
Common-space outdoor airflow measured.
HVAC functional testing of common-space and central systems.
Lighting controls tested.
225 CMR 23 C402.5.2.2 and C408
ENERGY STAR MFNC HVAC Functional Testing Checklist

Assembly Moisture Check

This section shows which air and vapor barriers are needed, and why.

Inputs

Item

Value

Climate zone

5A

Indoor air

70 F, 35% RH

Dewpoint of that indoor air

41 F

Outdoor air

9 F

Code

2021 IBC Section 1404.3, Table 1404.3(2)

Exterior Walls, floors 1-2 (steel studs), PROPOSED

Conclusion: This wall is 2x6 steel studs on floors 1-2. The dewpoint table is a wood-frame bay, so this wall has no bay table. The layers are gypsum, R-21 cavity insulation, plywood sheathing, R-3.8 continuous insulation, and vinyl cladding. R-3.8 continuous insulation is below the Class III minimum in 2021 IBC Table 1404.3(2) for a 2x6 wall in climate zone 5 (R-7.5), so the vapor retarder is Class II on the gypsum. The cavity insulation is air-permeable, so the air barrier is on the sheathing. Same at the rim. Keep the R-3.8 going over the band. The wood floors use that same continuous layer, so there is no insulation transition.

Exterior Walls, floors 3-5 (wood studs), PROPOSED

#

Layer (inside to outside)

R

Running R

Temp

Dewpoint target

Vs dewpoint

1

Drywall

1.13

1.13

67.4 F

41 F

OK

2

Class II vapor retarder

0.00

1.13

67.4 F

41 F

OK

3

R-21 cavity insulation with 2x6 wood studs

21.00

22.13

19.5 F

41 F

First below dewpoint

4

Wood sheathing

0.62

22.75

18.1 F

41 F

Below dewpoint

5

Air barrier

0.00

22.75

18.1 F

41 F

Below dewpoint

6

R-3.8 continuous insulation

3.80

26.55

9.4 F

41 F

Below dewpoint

7

Siding / cladding

0.17

26.72

9.0 F

41 F

Below dewpoint

Conclusion: Layer 3 is the first row below dewpoint. It is the cold plane we protect. Indoor moisture can turn to water if it gets there, and can eventually cause mold. It can get there two ways. It gets there through the drywall, which is why the vapor retarder is on the inside of the wall. It also gets there through holes (outlets, gaps, plates), which is why the air barrier is on the sheathing. Same at the rim. Keep the R-3.8 going over the band. The steel floors use this same R-3.8 continuous layer, so there is no insulation transition.

Exterior Walls, floors 1-2 (steel studs), HPWH

Conclusion: This wall is 2x6 steel studs on floors 1-2. The dewpoint table is a wood-frame bay, so this wall has no bay table. The layers are gypsum, R-21 cavity insulation, sheathing, R-5 continuous insulation, and cladding. R-5 continuous insulation is below the Class III minimum in 2021 IBC Table 1404.3(2) for a 2x6 wall in climate zone 5 (R-7.5), so the vapor retarder is Class II on the gypsum. The cavity insulation is air-permeable, so the air barrier is on the sheathing. Keep the R-5 going over the band.

Exterior Walls, floors 3-5 (wood studs), HPWH

#

Layer (inside to outside)

R

Running R

Temp

Dewpoint target

Vs dewpoint

1

Drywall

1.13

1.13

67.2 F

41 F

OK

2

Class II vapor retarder

0.00

1.13

67.2 F

41 F

OK

3

R-23 cavity insulation with 2x6 wood studs

23.00

24.13

10.9 F

41 F

First below dewpoint

4

Wood sheathing

0.62

24.75

9.4 F

41 F

Below dewpoint

5

Air barrier

0.00

24.75

9.4 F

41 F

Below dewpoint

6

Siding / cladding

0.17

24.92

9.0 F

41 F

Below dewpoint

Conclusion: Layer 3 is the first row below dewpoint. It is the cold plane we protect. Indoor moisture can turn to water if it gets there, and can eventually cause mold. It can get there two ways. It gets there through the drywall, which is why the vapor retarder is on the inside of the wall. It also gets there through holes (outlets, gaps, plates), which is why the air barrier is on the sheathing. Same at the rim.

Exterior Walls, steel stud alternative (both paths)

Conclusion: This is the alternative for the steel wall on both paths. It is not the specified wall. The studs are 2x6 steel. The dewpoint table is a wood-frame bay, so this wall has no bay table. The layers are gypsum, R-13 cavity insulation, sheathing, R-10 continuous insulation, and cladding. R-10 continuous insulation meets the Class III minimum in 2021 IBC Table 1404.3(2) for a 2x6 wall in climate zone 5 (R-7.5), so the vapor retarder is Class III on the gypsum. The cavity insulation is air-permeable, so the air barrier is on the sheathing. If this alternative is built, keep the R-10 going over the band.

Floor Over Unconditioned Space, R-30 cavity

#

Layer (inside to outside)

R

Running R

Temp

Dewpoint target

Vs dewpoint

1

Floor finish

1.13

1.13

67.8 F

41 F

OK

2

R-30 cavity insulation

30.00

31.13

9.3 F

41 F

First below dewpoint

3

Air barrier

0.00

31.13

9.3 F

41 F

Below dewpoint

4

Unconditioned

0.17

31.30

9.0 F

41 F

Below dewpoint

Conclusion: Layer 2 is the first row below dewpoint. It is the cold plane we protect. Indoor moisture can turn to water if it gets there, and can eventually cause mold. The spray foam is the vapor retarder. It can still get there through holes, which is why the air barrier is at the floor so unconditioned air cannot enter the unit.

Floor Over Unconditioned Space, R-19 cavity plus R-5 continuous

#

Layer (inside to outside)

R

Running R

Temp

Dewpoint target

Vs dewpoint

1

Floor finish

1.13

1.13

67.3 F

41 F

OK

2

R-19 cavity insulation

19.00

20.13

21.5 F

41 F

First below dewpoint

3

Air barrier

0.00

20.13

21.5 F

41 F

Below dewpoint

4

R-5 continuous insulation

5.00

25.13

9.4 F

41 F

Below dewpoint

5

Unconditioned

0.17

25.30

9.0 F

41 F

Below dewpoint

Conclusion: Layer 2 is the first row below dewpoint. It is the cold plane we protect. Indoor moisture can turn to water if it gets there, and can eventually cause mold. It can get there through holes, which is why the air barrier is at the insulated plane, not a drop-in ceiling.

Floor Over Unconditioned Space, R-13 cavity plus R-17 continuous

#

Layer (inside to outside)

R

Running R

Temp

Dewpoint target

Vs dewpoint

1

Floor finish

1.13

1.13

67.8 F

41 F

OK

2

R-13 cavity insulation

13.00

14.13

42.5 F

41 F

OK

3

Air barrier

0.00

14.13

42.5 F

41 F

OK

4

R-17 continuous insulation

17.00

31.13

9.3 F

41 F

First below dewpoint

5

Unconditioned

0.17

31.30

9.0 F

41 F

Below dewpoint

Conclusion: Layer 4 is the first row below dewpoint. It is the cold plane we protect. Indoor moisture can turn to water if it gets there, and can eventually cause mold. It can get there through holes, which is why the air barrier is at the insulated plane, not a drop-in ceiling.

Slab

#

Layer (inside to outside)

R

Running R

Temp

Dewpoint target

Vs dewpoint

1

Concrete slab

0.50

0.50

69.0 F

41 F

OK

2

Vapor retarder

0.00

0.50

69.0 F

41 F

OK

3

R-10 continuous at the perimeter

10.00

10.50

50.0 F

41 F

OK

4

Gravel / ground

0.00

10.50

50.0 F

41 F

OK

Conclusion: No row drops below dewpoint. This is not the wall problem. Indoor air is not leaking to a cold sheathing. The vapor retarder is under the slab to stop moisture coming up from the ground. The slab itself is the air barrier. This is the basement slab less than 10 ft below grade. Insulation is R-10 continuous at the perimeter.

Foundation / Below-Grade Walls, R-15 continuous

#

Layer (inside to outside)

R

Running R

Temp

Dewpoint target

Vs dewpoint

1

Drywall

1.13

1.13

65.9 F

41 F

OK

2

Air barrier

0.00

1.13

65.9 F

41 F

OK

3

R-15 continuous insulation

15.00

16.13

11.4 F

41 F

First below dewpoint

4

Concrete foundation wall

0.50

16.63

9.6 F

41 F

Below dewpoint

5

Soil

0.17

16.80

9.0 F

41 F

Below dewpoint

Conclusion: Layer 3 is the first row below dewpoint. It is the cold plane we protect. Indoor moisture can turn to water if it gets there, and can eventually cause mold. The continuous insulation is the vapor retarder. It can still get there through holes, which is why the air barrier is on the interior face of the insulation so room air cannot reach the cold concrete. This is the basement foundation wall, from the top of the wall to 10 ft below grade or the basement floor, whichever is less.

Foundation / Below-Grade Walls, R-19 cavity

#

Layer (inside to outside)

R

Running R

Temp

Dewpoint target

Vs dewpoint

1

Drywall

1.13

1.13

66.7 F

41 F

OK

2

Class II vapor retarder

0.00

1.13

66.7 F

41 F

OK

3

Air barrier

0.00

1.13

66.7 F

41 F

OK

4

R-19 cavity insulation

19.00

20.13

11.0 F

41 F

First below dewpoint

5

Concrete foundation wall

0.50

20.63

9.5 F

41 F

Below dewpoint

6

Soil

0.17

20.80

9.0 F

41 F

Below dewpoint

Conclusion: Layer 4 is the first row below dewpoint. It is the cold plane we protect. Indoor moisture can turn to water if it gets there, and can eventually cause mold. It can get there through the drywall, which is why the vapor retarder is Class II on the inside of the wall. It can also get there through holes, which is why the air barrier is on the interior face of the insulation so room air cannot reach the cold concrete. This is the basement foundation wall, from the top of the wall to 10 ft below grade or the basement floor, whichever is less.

Foundation / Below-Grade Walls, R-13 cavity plus R-5 continuous

#

Layer (inside to outside)

R

Running R

Temp

Dewpoint target

Vs dewpoint

1

Drywall

1.13

1.13

66.5 F

41 F

OK

2

Air barrier

0.00

1.13

66.5 F

41 F

OK

3

R-13 cavity insulation

13.00

14.13

26.5 F

41 F

First below dewpoint

4

R-5 continuous insulation

5.00

19.13

11.1 F

41 F

Below dewpoint

5

Concrete foundation wall

0.50

19.63

9.5 F

41 F

Below dewpoint

6

Soil

0.17

19.80

9.0 F

41 F

Below dewpoint

Conclusion: Layer 3 is the first row below dewpoint. It is the cold plane we protect. Indoor moisture can turn to water if it gets there, and can eventually cause mold. The continuous insulation is the vapor retarder. It can still get there through holes, which is why the air barrier is on the interior face of the insulation so room air cannot reach the cold concrete. This is the basement foundation wall, from the top of the wall to 10 ft below grade or the basement floor, whichever is less.

Roof (sealed attic), PROPOSED

#

Layer (inside to outside)

R

Running R

Temp

Dewpoint target

Vs dewpoint

1

Interior / attic

0.68

0.68

68.7 F

41 F

OK

2

Roof deck

0.62

1.30

67.5 F

41 F

OK

3

Air barrier

0.00

1.30

67.5 F

41 F

OK

4

R-30 continuous insulation

30.00

31.30

9.3 F

41 F

First below dewpoint

5

Roofing

0.17

31.47

9.0 F

41 F

Below dewpoint

Conclusion: Layer 4 is the first row below dewpoint. That plane is outside the deck, in the continuous insulation. The deck stays warm. Indoor moisture can turn to water if it gets to a cold face, and can eventually cause mold. The air barrier is on the deck so room air cannot leak into the insulation.

Roof (sealed attic), common area and HPWH

#

Layer (inside to outside)

R

Running R

Temp

Dewpoint target

Vs dewpoint

1

Gypsum ceiling

1.13

1.13

68.6 F

41 F

OK

2

Air barrier

0.00

1.13

68.6 F

41 F

OK

3

R-19 at the underside of the deck

19.00

20.13

45.9 F

41 F

OK

4

Roof deck

0.62

20.75

45.1 F

41 F

OK

5

R-30 continuous insulation

30.00

50.75

9.2 F

41 F

First below dewpoint

6

Roofing

0.17

50.92

9.0 F

41 F

Below dewpoint

Conclusion: Layer 5 is the first row below dewpoint. It is the cold plane we protect. Indoor moisture can turn to water if it gets there, and can eventually cause mold. It can get there through the insulation strapped under the deck, which is why the air barrier is the sealed gypsum on the room side of that insulation. The layer on the deck does not satisfy this.

Exterior Walls, floors 1-2, 2x6 steel, R-21 cavity plus R-3.8 continuous (Recommended Design)

Exterior Walls, floors 1-2, 2x6 steel, R-21 cavity plus R-3.8 continuous (Recommended Design)

Exterior Walls, floors 3-5, 2x6 wood, R-21 cavity plus R-3.8 continuous (Recommended Design)

Exterior Walls, floors 3-5, 2x6 wood, R-21 cavity plus R-3.8 continuous (Recommended Design)

Exterior Walls, floors 1-2, 2x6 steel, R-21 cavity plus R-5 continuous (HPWH)

Exterior Walls, floors 1-2, 2x6 steel, R-21 cavity plus R-5 continuous (HPWH)

Exterior Walls, floors 3-5, 2x6 wood, R-23 cavity, no continuous insulation (HPWH)

Exterior Walls, floors 3-5, 2x6 wood, R-23 cavity, no continuous insulation (HPWH)

Exterior Walls, steel stud alternative, R-13 cavity plus R-10 continuous (both paths)

Exterior Walls, steel stud alternative, R-13 cavity plus R-10 continuous (both paths)

Floor Over Unconditioned Space, R-30 cavity (common area)

Floor Over Unconditioned Space, R-30 cavity (common area)

Floor Over Unconditioned Space, R-19 cavity plus R-5 continuous (common area)

Floor Over Unconditioned Space, R-19 cavity plus R-5 continuous (common area)

Floor Over Unconditioned Space, R-13 cavity plus R-17 continuous (common area)

Floor Over Unconditioned Space, R-13 cavity plus R-17 continuous (common area)

Basement slab, R-10 continuous at the perimeter (common area)

Basement slab, R-10 continuous at the perimeter (common area)

Foundation / Below-Grade Walls, R-15 continuous (common area)

Foundation / Below-Grade Walls, R-15 continuous (common area)

Foundation / Below-Grade Walls, R-19 cavity (common area)

Foundation / Below-Grade Walls, R-19 cavity (common area)

Foundation / Below-Grade Walls, R-13 cavity plus R-5 continuous (common area)

Foundation / Below-Grade Walls, R-13 cavity plus R-5 continuous (common area)

Roof, sealed attic, R-30 continuous (Recommended Design)

Roof, sealed attic, R-30 continuous (Recommended Design)

Roof, sealed attic, R-19 underside plus R-30 continuous (common area and HPWH)

Roof, sealed attic, R-19 underside plus R-30 continuous (common area and HPWH)

Rim Joists, R-21 cavity, R-3.8 continuous over the band (Recommended Design)

Rim Joists, R-21 cavity, R-3.8 continuous over the band (Recommended Design)

Path Comparison

This section shows the detailed requirements and incentives for each path we compared, basically showing our work of how we determined the recommended path is the most affordable way of meeting energy code compliance.

Path Comparison - Incentives

PROPOSED / HPWH: $71,750 - $133,250

  • MassSave Multifamily Program Energy Star Tier ($71,750) (Program Breakdown): You get this rebate for having your building(s) certified for the Energy Star MFNC v1.2 program. This requires pre-approval via an application to be submitted before construction starts. This rebate comes in the form of a check within 4 months of certification documentation being provided to MassSave, typically this is 4 months after construction is complete.
  • DOER Alternative Energy Credits ($0 - $61,500) (Program Breakdown): This rebate is received for installing APS eligible air source heat pumps (click here for the list). There is an extensive process to get this incentive. It comes in the form of a check approximately 6-12 months after the heat pumps are installed and fully operational.
    • IMPORTANT: Although an estimate is provided, this incentive can vary widely typically between $300-1,500 per heat pump. It's based on expected kWh usage of the system as well as the market value of the alternative energy credits when sold.
    • Risks: Massachusetts is rewriting this program right now. The House bill would stop the state from accepting new applications on January 1, 2028, the Senate version leaves heat pumps out of that cutoff, and the two are in conference. The application needs the equipment installed and operating, so a project that will not reach that point before the deadline should treat this as upside rather than a budgeted line.

Path Comparison - Net Cost Summary

Path

Total Cost $/sf

Total Incentives $/sf

Net $/sf

OpEx Factor

PROPOSED

$59.32

$1.90

$58.46

1.02

HPWH

$61.37

$1.90

$60.64

1.02

Path Comparison - Envelope

Item

Path

Detailed Specifications

Cost $/sf

Incentive $/sf

Net $/sf

OpEx

Exterior Walls

HPWH

Floors 1-2: ≥ R-21 cavity insulation (2x6 steel @ 16" o.c.) with ≥ R-5 continuous exterior insulation. Floors 3-5: ≥ R-23 cavity insulation (2x6 wood @ 16" o.c.), no continuous insulation. Suitable alternative for the steel wall: ≥ R-13 cavity plus ≥ R-10 continuous.

$5.91

$0.00

$5.91

0.95

PROPOSED

Floors 1-2: ≥ R-21 cavity insulation (2x6 steel @ 16" o.c., 5.5 in) with ≥ R-3.8 polyiso continuous exterior insulation (1 in). Floors 3-5: ≥ R-21 cavity insulation (2x6 wood @ 16" o.c., 5.5 in) with ≥ R-3.8 polyiso continuous exterior insulation (1 in). Steel and wood share the same R-3.8 continuous insulation, so there is no insulation transition between floors. Suitable alternative for the steel wall: ≥ R-13 cavity plus ≥ R-10 continuous.

$6.56

$0.00

$6.56

0.90

Below Grade Walls

HPWH

N/A

$0.00

$0.00

$0.00

1.00

PROPOSED

N/A

$0.00

$0.00

$0.00

1.00

Corridor Walls

HPWH

N/A

$0.00

$0.00

$0.00

1.00

PROPOSED

N/A

$0.00

$0.00

$0.00

1.00

Slab

HPWH

N/A

$0.00

$0.00

$0.00

1.00

PROPOSED

N/A

$0.00

$0.00

$0.00

1.00

Floor Over Unconditioned Space

HPWH

N/A

$0.00

$0.00

$0.00

1.00

PROPOSED

N/A

$0.00

$0.00

$0.00

1.00

Floor Over Garage

HPWH

N/A

$0.00

$0.00

$0.00

1.00

PROPOSED

N/A

$0.00

$0.00

$0.00

1.00

Floor Over Podium

HPWH

N/A

$0.00

$0.00

$0.00

1.00

PROPOSED

N/A

$0.00

$0.00

$0.00

1.00

Rim Joists

HPWH

≥ R-21 rim/band insulation at floor transitions.

$0.20

$0.00

$0.20

0.95

PROPOSED

≥ R-21 rim/band insulation at floor transitions.

$0.20

$0.00

$0.20

0.95

Roof

HPWH

Sealed attic: ≥ R-19 insulation + ≥ R-30 continuous insulation.

$2.79

$0.00

$2.79

1.10

PROPOSED

Sealed attic: ≥ R-30 continuous insulation.

$1.40

$0.00

$1.40

1.10

Windows & Glass Doors

HPWH

High performance, U ≤ 0.25 / SHGC ≤ 0.25.

$9.49

$0.00

$9.49

1.00

PROPOSED

High performance, U ≤ 0.27 / SHGC ≤ 0.30.

$8.18

$0.00

$8.18

1.00

Doors

HPWH

Opaque door, U ≤ 0.20 (R-5.0).

$0.35

$0.00

$0.35

0.95

PROPOSED

Opaque door, U ≤ 0.20 (R-5.0).

$0.35

$0.00

$0.35

0.95

Air Sealing

HPWH

≤ 0.27 CFM50 per sqft of shell; tested.

$1.29

$0.00

$1.29

0.95

PROPOSED

≤ 0.27 CFM50 per sqft of shell; tested.

$1.29

$0.00

$1.29

0.95

Path Comparison - Mechanical

Item

Path

Detailed Specifications

Cost $/sf

Incentive $/sf

Net $/sf

OpEx

HVAC

HPWH

Ducted air-source heat pump (as modeled); SEER2 ≥ 17.5; HSPF2 ≥ 10.5. See HVAC Design Loads.

$15.82

$0.00

$15.82

1.15

PROPOSED

Ducted air-source heat pump (as modeled); SEER2 ≥ 17.5; HSPF2 ≥ 10.5. See HVAC Design Loads.

$15.82

$0.00

$15.82

1.15

Ductwork

HPWH

Supply and return ducts in conditioned space insulated to code minimum.

$5.18

$0.00

$5.18

1.00

PROPOSED

Supply and return ducts in conditioned space insulated to code minimum.

$5.18

$0.00

$5.18

1.00

Duct Sealing

HPWH

≤ greater of 80 CFM25 or 8 CFM25 per 100 sqft of conditioned floor area; tested at final.

$0.89

$0.00

$0.89

1.00

PROPOSED

≤ greater of 80 CFM25 or 8 CFM25 per 100 sqft of conditioned floor area; tested at final.

$0.89

$0.00

$0.89

1.00

HVAC Grading

HPWH

Fan Flow Test: Grade II
Watt Draw Test: Grade II
Refrigerant Charge: Grade I (weigh-in method)
HVAC installer must provide photo of the digital refrigerant scale showing the amount charged, with the tank on the scale and hoses connected to the outdoor unit, along with a photo of the outdoor unit's data plate.
If the non-invasive procedure in ANSI / RESNET / ACCA 310 is not permitted to be used during the final inspection of a unit (i.e., due to the equipment type or to outdoor air temperatures that do not meet the requirements of the non-invasive method), then the unit is permitted to be certified with a default refrigerant charge designation of Grade III. Note that in these circumstances, the weigh-in method procedure in ANSI / RESNET / ACCA 310 may still be used to pursue a Grade I designation.

$0.00

$0.00

$0.00

1.00

PROPOSED

Fan Flow Test: Grade II
Watt Draw Test: Grade II
Refrigerant Charge: Grade I (weigh-in method)
HVAC installer must provide photo of the digital refrigerant scale showing the amount charged, with the tank on the scale and hoses connected to the outdoor unit, along with a photo of the outdoor unit's data plate.
If the non-invasive procedure in ANSI / RESNET / ACCA 310 is not permitted to be used during the final inspection of a unit (i.e., due to the equipment type or to outdoor air temperatures that do not meet the requirements of the non-invasive method), then the unit is permitted to be certified with a default refrigerant charge designation of Grade III. Note that in these circumstances, the weigh-in method procedure in ANSI / RESNET / ACCA 310 may still be used to pursue a Grade I designation.

$0.00

$0.00

$0.00

1.00

Mechanical Ventilation

HPWH

In-unit ERV
1-bedroom: 70 CFM, ≥ 87% ASRE
2-bedroom: 90 CFM, ≥ 81% ASRE
3-bedroom: 90 CFM, ≥ 81% ASRE

$2.28

$0.00

$2.28

1.20

PROPOSED

In-unit ERV
1-bedroom: 70 CFM, ≥ 87% ASRE
2-bedroom: 90 CFM, ≥ 81% ASRE
3-bedroom: 90 CFM, ≥ 81% ASRE

$2.28

$0.00

$2.28

1.20

Local Mechanical Exhaust

HPWH

Bathroom(s): at least 50 CFM intermittent and up to 3.0 sones, or at least 20 CFM continuous and up to 2.0 sones.
Kitchen(s): at least 100 CFM intermittent and up to 3.0 sones, or continuous at 5 ACH.
Both: exhaust directly outdoors with ENERGY STAR certified fans. A balanced ERV or HRV serving the space may satisfy this requirement.

$1.26

$0.00

$1.26

1.05

PROPOSED

Bathroom(s): at least 50 CFM intermittent and up to 3.0 sones, or at least 20 CFM continuous and up to 2.0 sones.
Kitchen(s): at least 100 CFM intermittent and up to 3.0 sones, or continuous at 5 ACH.
Both: exhaust directly outdoors with ENERGY STAR certified fans. A balanced ERV or HRV serving the space may satisfy this requirement.

$1.26

$0.00

$1.26

1.05

Thermostats

HPWH

Programmable thermostat (as modeled).

$0.15

$0.00

$0.15

1.05

PROPOSED

Programmable thermostat (as modeled).

$0.15

$0.00

$0.15

1.05

Path Comparison - Plumbing & Appliances

Item

Path

Detailed Specifications

Cost $/sf

Incentive $/sf

Net $/sf

OpEx

DHW

HPWH

1-Bedroom: Heat pump water heater (HPWH) (as modeled); UEF ≥ 3.88; 40 gal
2-Bedroom: Heat pump water heater (HPWH) (as modeled); UEF ≥ 3.88; 50 gal
3-Bedroom: Heat pump water heater (HPWH) (as modeled); UEF ≥ 3.88; 65 gal

$3.40

$0.00

$3.40

1.20

PROPOSED

1-Bedroom: Heat pump water heater (HPWH) (as modeled); UEF ≥ 3.88; 40 gal
2-Bedroom: Heat pump water heater (HPWH) (as modeled); UEF ≥ 3.88; 50 gal
3-Bedroom: Heat pump water heater (HPWH) (as modeled); UEF ≥ 3.88; 65 gal

$3.40

$0.00

$3.40

1.20

DHW Piping

HPWH

Supply piping insulated to ≥ R-3.

$0.89

$0.00

$0.89

0.95

PROPOSED

Supply piping insulated to ≥ R-3.

$0.89

$0.00

$0.89

0.95

Water Fixtures

HPWH

WaterSense certified (Lavatory ≤ 1.2 GPM; Shower ≤ 2.0 GPM; Kitchen ≤ 2.2 GPM).

$2.22

$0.00

$2.22

1.00

PROPOSED

WaterSense certified (Lavatory ≤ 1.2 GPM; Shower ≤ 2.0 GPM; Kitchen ≤ 2.2 GPM).

$2.22

$0.00

$2.22

1.00

Refrigerator

HPWH

≤ 600 kWh/yr; electric.

$0.90

$0.00

$0.90

1.10

PROPOSED

≤ 600 kWh/yr; electric.

$0.90

$0.00

$0.90

1.10

Dishwasher

HPWH

≤ 269 kWh/yr; electric.

$0.52

$0.00

$0.52

1.10

PROPOSED

≤ 269 kWh/yr; electric.

$0.52

$0.00

$0.52

1.10

Clothes Washer

HPWH

IMEF ≥ 2.06; IWF ≤ 4.2; ≤ 152 kWh/yr; electric.

$0.63

$0.00

$0.63

1.10

PROPOSED

IMEF ≥ 2.06; IWF ≤ 4.2; ≤ 152 kWh/yr; electric.

$0.63

$0.00

$0.63

1.10

Clothes Dryer

HPWH

Heat pump dryer; ventless; CEF ≥ 6.

$1.22

$0.00

$1.22

1.00

PROPOSED

Heat pump dryer; ventless; CEF ≥ 6.

$1.22

$0.00

$1.22

1.00

Stove / Oven

HPWH

Electric range.

$0.71

$0.00

$0.71

1.00

PROPOSED

Electric range.

$0.71

$0.00

$0.71

1.00

Path Comparison - Electrical

Item

Path

Detailed Specifications

Cost $/sf

Incentive $/sf

Net $/sf

OpEx

Lighting

HPWH

≥ 100% high-efficacy (LED).

$4.00

$0.00

$4.00

0.85

PROPOSED

≥ 100% high-efficacy (LED).

$4.00

$0.00

$4.00

0.85

Solar Ready

HPWH

N/A

$0.00

$0.00

$0.00

1.00

PROPOSED

N/A

$0.00

$0.00

$0.00

1.00

EV Ready

HPWH

At least 20% of parking spaces wired EV-ready (40-amp Level II; shared circuits with load management allowed).

$0.46

$0.00

$0.46

1.00

PROPOSED

At least 20% of parking spaces wired EV-ready (40-amp Level II; shared circuits with load management allowed).

$0.46

$0.00

$0.46

1.00

HPWH Ready

HPWH

N/A

$0.00

$0.00

$0.00

1.00

PROPOSED

N/A

$0.00

$0.00

$0.00

1.00

Path Comparison - Soft Costs & Whole-Building Incentives

Item

Path

Detailed Specifications

Cost $/sf

Incentive $/sf

Net $/sf

OpEx

Paperwork & Modeling

HPWH

ENERGY STAR energy model to the target (per-unit HERS or whole-building ASHRAE path), the ENERGY STAR design-review checklist and multifamily workbook, and an HVAC design report.

$0.24

$1.90

-$1.66

1.00

PROPOSED

ENERGY STAR energy model to the target (per-unit HERS or whole-building ASHRAE path), the ENERGY STAR design-review checklist and multifamily workbook, and an HVAC design report.

$0.24

$1.90

-$1.66

1.00

Testing & Verification

HPWH

ENERGY STAR field verification: pre-drywall and final inspections, unit air-tightness (blower door), duct-leakage, ventilation and exhaust airflow, and HVAC functional testing.

$0.57

$0.00

$0.57

1.00

PROPOSED

ENERGY STAR field verification: pre-drywall and final inspections, unit air-tightness (blower door), duct-leakage, ventilation and exhaust airflow, and HVAC functional testing.

$0.57

$0.00

$0.57

1.00

Additional Design Considerations Not Represented In This Study

  • Smaller Heat Pumps on the Two- and Three-Bedroom Units: A smaller heat pump sized to the cooling load was not used on the two-bedroom or three-bedroom units, because heating at 5 F set the size. On both the HPWH and PROPOSED paths those units stay single-stage ducted heat pumps at 24 kBtuh. ENERGY STAR MFNC holds a single-stage unit to 130 percent of the cooling load. Cooling is over that limit on both paths: the HPWH two-bedroom is 176.5 percent of its 13.6 kBtuh cooling load and the HPWH three-bedroom is 165.5 percent of its 14.5 kBtuh load, and the PROPOSED two-bedroom is 169.0 percent of its 14.2 kBtuh load and the PROPOSED three-bedroom is 158.9 percent of its 15.1 kBtuh load. Heating at 5 F still passes, so the smaller cooling size was not used. The one-bedroom units are 12 kBtuh and pass cooling on both paths.