CS86 Energy Code Feasibility Study in Brockton, Massachusetts
Energy code feasibility study for a 36-unit high-rise in Massachusetts. Compares multiple design paths. Recommended: ELECTRIC (All-Electric). View full study.
- Study Type
- Energy Code Feasibility Study
- State
- Massachusetts
- Units
- 36
- Building Type
- high-rise
- Fuel Type
- Mixed Fuel
- Recommended Path
- ELECTRIC (All-Electric)
Goal
To find the most cost-effective compliance path, this report isolates energy code related costs from total construction. We use real bid data from vendors & clients to create a reliable framework for aligning incentives and design, with all recommendations confirmed by detailed energy modeling.
Project
- Brockton, MA 02301
- 1 Building | 36 Units | 33,414 SF Conditioned
- Substantial rehab & addition | 6-story high-rise multifamily (x1)
- All-Electric OR Mixed Fuel | 2021 IECC with MA Amendments (Stretch Code) | HERS ≤ 58 (All-Electric) OR HERS ≤ 55 (Mixed Fuel) | ENERGY STAR MFNC v1.1
Overview
Read This: This report compares different ways you can build the project and meet energy code, looking at both cost and incentives, with the ultimate goal as finding the most affordable path.
- The overview outlines the key differences between each of the paths we show in this report and why we recommend the one we picked over the others.
- The recommended design section is where we share the requirements and incentives for the path we think is best based on affordability.
- The path comparison section shows the detailed requirements and incentives for each path we compared, basically showing our work if you want to dig in.
Product Recs: All product recommendations are recommendations only and can be substituted with any equivalent or better match.
Path Summaries
All three paths meet the Massachusetts Stretch Code and are modeled to pass on a lean margin. ELECTRIC is the lowest net cost. GAS-HEAT and CURRENT are great alternatives when the fuel mix should be different.
ELECTRIC (All-Electric): Recommended
This is the least expensive path at approximately $49.82/sf net, and it is the simplest of the three to build. It keeps the project fully electric, which preserves the $36,000 Mass Save Base multifamily high-rise incentive ($1,000 per unit) and aligns with the direction Massachusetts energy code is heading. The wall air barrier sits on the sheathing and the roof air barrier sits on the deck with the cold plane outside the deck, and for this project this is the right choice.
GAS-HEAT (Mixed-Fuel): Alternative
A great alternative at approximately $50.58/sf net, about $0.76/sf more than the ELECTRIC path. Choose it when the building should heat with gas: an 85 AFUE furnace, separate cooling, and Teal's centralized condensing water heater with two 100 gallon tanks. It does not earn the Mass Save Base incentive because the heat is gas.
CURRENT (Mixed-Fuel): Alternative
A great alternative at approximately $52.89/sf net, about $3/sf more than the ELECTRIC path. Heating stays electric, so it keeps the same $36,000 Mass Save Base incentive, and hot water is Teal's centralized condensing system. Choose it when the project wants heat pumps and gas water heating.
What Changes Between Paths
Item | CURRENT | GAS-HEAT | ELECTRIC (Recommended) |
|---|---|---|---|
HVAC | Ducted air-source heat pump; SEER2 ≥ 16; HSPF2 ≥ 8.5. See HVAC Design Loads. | Natural gas furnace; AFUE ≥ 85; cooling by a separate system, cooling only; SEER2 ≥ 16. See HVAC Design Loads. | Ducted air-source heat pump; SEER2 ≥ 16; HSPF2 ≥ 8.5. See HVAC Design Loads. |
DHW | Centralized gas water heating system with two 100 gallon tanks and a temperature-controlled recirculating system; ≥ 0.80 energy factor. | Centralized gas water heating system with two 100 gallon tanks and a temperature-controlled recirculating system; ≥ 0.85 energy factor. | Electric resistance storage water heater; UEF ≥ 0.92; 50 gal. |
Cost $/sf | $53.26 | $49.97 | $50.38 |
Incentive $/sf | $1.08 | $0.00 | $1.08 |
Net $/sf | $52.89 | $50.58 | $49.82 |
Permit / Certificate of Occupancy Requirements

High Rise Buildings

Code Path
- HERS: Brockton is a Stretch Code town. The buildings are 6-story Group R under 225 CMR 23. Existing-building work follows Chapter 5 (sections C501.2, C502 and C503). The dwelling units comply by per-unit HERS under section C407.4. The all-electric Stretch ceiling is HERS ≤ 58 and the mixed-fuel Stretch ceiling is HERS ≤ 55 (Table C407.4, Major alterations, additions, or change of use column, footnote b), prior to onsite renewable electric generation (footnote a). Section C407.4.1 requires the building to meet ENERGY STAR Multifamily New Construction.
Permit Requirements
- HERS: With the building permit application, per 225 CMR 23 section C407.4.2.1: the proposed HERS Index on the title page and plans, the rater's name, the software name and version, all modeled inputs, and a certificate showing each dwelling unit type at or below the Table C407.4 ceiling for its fuel, with the component specifications behind it (insulation R-values and U-factors, assumed duct and envelope leakage, and heating, cooling, ventilation, and water-heating types and efficiencies), on the worst-case orientation where no site-specific report is produced. ENERGY STAR Multifamily New Construction design review by the rater is part of that package (C407.4.1).
Certificate of Occupancy Requirements
- HERS: Before certificate of occupancy, per 225 CMR 23 section C407.4.2.2: the final HERS Index on the title page and plans, a confirmed as-built HERS certificate for each rated unit with the duct and envelope air-leakage test results and the installed equipment efficiencies, and documentation that each unit meets ENERGY STAR Multifamily New Construction (item 7). C405.13 EV-ready and Appendix CB solar-ready compliance close out with it (item 9). A certified HERS rater verifies the package (C407.4.3). Air-leakage testing follows ANSI/RESNET/ICC 380, and RESNET sampling is permitted because each building has more than 8 units (C402.5.2.2).
Recommended Design
This section outlines the design requirements, product recommendations, and incentives for the design that we believe will be the most affordable path to meeting energy code.
Recommended Design - Incentives
Incentives Available: $36,000 - $90,000
- MassSave Multifamily High Rise Program Base Tier ($36,000) (Program Breakdown): You get this rebate for having your building(s) meet energy code. This requires pre-approval via an application to be submitted before construction starts. This rebate comes in the form of a check within 4 months of certification documentation being provided to MassSave, typically this is 4 months after construction is complete.
- DOER Alternative Energy Credits ($0 - $54,000) (Program Breakdown): This rebate is received for installing APS eligible air source heat pumps (click here for the list). There is an extensive process to get this incentive. It comes in the form of a check approximately 6-12 months after the heat pumps are installed and fully operational.
- IMPORTANT: Although an estimate is provided, this incentive can vary widely typically between $300-1,500 per heat pump. It's based on expected kWh usage of the system as well as the market value of the alternative energy credits when sold.
- Risks: Massachusetts is rewriting this program right now. The House bill would stop the state from accepting new applications on January 1, 2028, the Senate version leaves heat pumps out of that cutoff, and the two are in conference. The application needs the equipment installed and operating, so a project that will not reach that point before the deadline should treat this as upside rather than a budgeted line.
HVAC Design Loads
Plymouth County, MA · heating 9.0°F/70.0°F · cooling 88.0°F/75.0°F · all values kBtuh
Design heat loss · components
Unit type | Walls & rim joists | Roof / ceiling | Slab, floors & below grade | Windows & doors | Infiltration | Ventilation | Design heat loss | Design heat loss at selection |
|---|---|---|---|---|---|---|---|---|
2-Bedroom | 4.4 | 1.6 | 0.0 | 3.9 | 6.1 | 2.4 | 18.4 @ 9°F | 19.6 @ 5°F |
3-Bedroom | 3.9 | 1.4 | 0.0 | 6.9 | 6.3 | 2.4 | 21.0 @ 9°F | 22.3 @ 5°F |
Design heat gain · components
Unit type | Solar through glazing | Envelope conduction | Internal gains | Infiltration & ventilation | Latent | Total heat gain | Sensible heat ratio |
|---|---|---|---|---|---|---|---|
2-Bedroom | 1.7 | 2.2 | 2.3 | 2.6 | 4.3 | 13.1 | 0.67 |
3-Bedroom | 5.7 | 2.7 | 2.5 | 2.6 | 4.6 | 18.2 | 0.75 |
Selection
Unit type | Cooling Capacity | Minimum Heating Capacity |
|---|---|---|
2-Bedroom | 11.8 to 20.0 kBtuh rated | ≥ 19.6 kBtuh @ 5°F |
3-Bedroom | 16.4 to 23.7 kBtuh rated | ≥ 22.3 kBtuh @ 5°F |
ENERGY STAR Total UA
Item | Detail |
|---|---|
Climate zone | IECC 5A (2012 IECC map) |
Program | ENERGY STAR MFNC National v1.1 Rev. 05 |
Rule | Design Review Item 2.1 / Fn 11-12; Proposed UA ≤ Reference UA |
Code reference | Exhibit 1 Table 1 (2012 IECC CZ); Design Review Item 2.1 / Fn 11-12 |
Version basis | v1.1 |
Note | Reference wall U for the exterior wall is U-0.089. Proposed wall U stays the Ekotrope assembly U. Proposed U for walls, roof, windows, doors is the area-weighted Ekotrope assembly U. Any component without an Ekotrope U keeps the spec lookup. Proposed wall U 0.060 is the area-weighted Ekotrope assembly U (0.060). The v1.1 wood-framed-wall exception is the Reference U in this table (0.089), not a replacement for a better Ekotrope U. |
Assembly | Proposed spec |
|---|---|
Walls | Existing brick walls (stories 1-4): closed-cell spray foam filling the 2x6 cavity, against the existing wood sheathing. The foam is the air barrier and the vapor retarder. |
Roof | Sealed attic: ≥ R-30 continuous insulation. |
Windows | Double pane, U ≤ 0.30 / SHGC 0.30-0.40. |
Doors | Opaque door, U ≤ 0.20 (R-5.0). |
Slab | N/A |
Envelope Takeoffs
Building | Opaque walls (sf) | Roof (sf) | Windows (sf) |
|---|---|---|---|
43 | 23,229 | 5,928 | 4,134 |
Component UA
Component | Quantity | Proposed U or F | Proposed UA | Reference U or F | Reference UA |
|---|---|---|---|---|---|
Opaque exterior walls | 23,229 sf | 0.060 | 1,388 | 0.089 | 2,067 |
Roof / ceiling | 5,928 sf | 0.030 | 178 | 0.021 | 124 |
Windows & glass doors | 4,134 sf | 0.300 | 1,240 | 0.270 | 1,116 |
Total UA
Building | Proposed UA | Reference UA | % of reference | Result |
|---|---|---|---|---|
43 | 2,806 | 3,308 | 84.8% | PASS |
Site total | 2,806 | 3,308 | 84.8% | PASS |
Recommended Design - Units
Item | Detailed Specifications |
|---|---|
Exterior Walls | Existing brick walls (stories 1-4): R-21 closed-cell spray foam against the existing wood sheathing. The foam is the air barrier and the vapor retarder. |
Below Grade Walls | N/A |
Corridor Walls | N/A |
Slab | N/A |
Floor Over Unconditioned Space | N/A |
Floor Over Garage | N/A |
Floor Over Podium | N/A |
Rim Joists | Stories 1-4: R-21 closed-cell spray foam at the rim band, tight to the sheathing. The foam is the air barrier. |
Roof | Sealed attic: ≥ R-30 continuous insulation. |
Windows & Glass Doors | Double pane, U ≤ 0.30 / SHGC 0.30-0.40. (Product Rec). |
Doors | Opaque door, U ≤ 0.20 (R-5.0). |
Air Sealing | ≤ 0.30 CFM50 per sqft of enclosure (compartmentalization); tested. (Air Sealing Protocol) |
HVAC | Ducted air-source heat pump; SEER2 ≥ 16; HSPF2 ≥ 8.5. See HVAC Design Loads. (Product Rec). |
Ductwork | Supply and return ducts in conditioned space insulated to code minimum. |
Duct Sealing | ≤ greater of 80 CFM25 or 8 CFM25 per 100 sqft of conditioned floor area; tested at final. (Duct Sealing Protocol) |
HVAC Grading | Fan Flow Test: Grade II |
Mechanical Ventilation | In-unit ERV (Product Rec). |
Local Mechanical Exhaust | Bathroom(s): at least 50 CFM intermittent and up to 3.0 sones, or at least 20 CFM continuous and up to 2.0 sones. |
Thermostats | Programmable thermostat. |
DHW | Electric resistance storage water heater; UEF ≥ 0.92; 50 gal. (Product Rec). |
DHW Piping | Supply piping insulated to ≥ R-3. |
Water Fixtures | WaterSense certified (Lavatory ≤ 1.2 GPM; Shower ≤ 2.0 GPM; Kitchen ≤ 2.2 GPM). |
Refrigerator | ≤ 650 kWh/yr; electric. (Product Rec). |
Dishwasher | ≤ 269 kWh/yr; electric. (Product Rec). |
Clothes Washer | IMEF ≥ 2.06; IWF ≤ 4.2; ≤ 152 kWh/yr; electric. (Product Rec). |
Clothes Dryer | Standard electric dryer; vented; CEF ≥ 3.93. (Product Rec). |
Stove / Oven | Electric range. (Product Rec). |
Lighting | ≥ 100% high-efficacy (LED). |
Solar Ready | A solar system will be installed, so solar-ready requirements are exempt. |
EV Ready | 20% of parking spaces EV-ready. |
HPWH Ready | N/A |
Paperwork & Modeling | ENERGY STAR energy model to the target (per-unit HERS or whole-building ASHRAE path), the ENERGY STAR design-review checklist and multifamily workbook, and an HVAC design report. |
Testing & Verification | ENERGY STAR field verification: pre-drywall and final inspections, unit air-tightness (blower door), duct-leakage, ventilation and exhaust airflow, and HVAC functional testing. |
Recommended Design - Common Areas
Item | Common Areas (Residential Building) |
|---|---|
Exterior Walls | Existing brick walls (stories 1-4): R-21 closed-cell spray foam against the existing wood sheathing. The foam is the air barrier and the vapor retarder. |
Below Grade Walls | N/A |
Corridor Walls | N/A |
Slab | N/A |
Floor Over Unconditioned Space | N/A |
Floor Over Garage | N/A |
Floor Over Podium | N/A |
Rim Joists | Stories 1-4: R-21 closed-cell spray foam at the rim band, tight to the sheathing. The foam is the air barrier. |
Roof | Sealed attic: ≥ R-30 continuous insulation. |
Windows & Glass Doors | Fixed U ≤ 0.34. |
Doors | Glazed entrance U ≤ 0.60. |
Air Sealing | Continuous air barrier for these spaces. |
HVAC | Ducted split heat pump: HSPF2 7.8 / SEER2 15.2. |
Ductwork | Ducts and air handlers serving these spaces are in conditioned space. |
Duct Sealing | Supply, return, and exhaust ducts and plenums serving these spaces are sealed at transverse joints, longitudinal seams, and duct wall penetrations. |
HVAC Grading | N/A |
Mechanical Ventilation | Outdoor air to the community space and the hallways, at the ASHRAE 62.1 Section 6 rate for that space. |
Local Mechanical Exhaust | N/A |
Thermostats | Programmable thermostat. |
DHW | electric tank or instant hot water heater, UEF ≥ 0.93 |
DHW Piping | N/A |
Water Fixtures | WaterSense bathroom faucets, aerators, and showerheads. |
Refrigerator | N/A |
Dishwasher | N/A |
Clothes Washer | N/A |
Clothes Dryer | N/A |
Stove / Oven | N/A |
Lighting | 100% LED. |
Lighting Controls | Occupant sensors in the community space, hallways, and basement storage. |
Solar Ready | A solar system will be installed, so solar-ready requirements are exempt. |
EV Ready | 20% of parking spaces EV-ready. |
HPWH Ready | N/A |
Electric Readiness | N/A |
Vestibules | N/A |
Efficiency Credits | N/A |
Paperwork & Modeling | HERS index certificate at permit and at certificate of occupancy. |
Testing & Verification | Hallways and enclosed common spaces not greater than 1,500 sqft verified by inspection of the continuous air barrier. |
Assembly Moisture Check
This section shows which air and vapor barriers are needed, and why.
Inputs
Item | Value |
|---|---|
Climate zone | 5A |
Indoor air | 70 F, 35% RH |
Dewpoint of that indoor air | 41 F |
Outdoor air | 9 F |
Code | 2021 IBC Section 1404.3, Table 1404.3(2) |
New walls (stories 5-6)
# | Layer (inside to outside) | R | Running R | Temp | Dewpoint target | Vs dewpoint |
|---|---|---|---|---|---|---|
1 | Drywall | 1.13 | 1.13 | 67.0 F | 41 F | OK |
2 | Class II vapor retarder | 0.00 | 1.13 | 67.0 F | 41 F | OK |
3 | R-21 cavity insulation with 2x6 wood studs | 21.00 | 22.13 | 11.1 F | 41 F | First below dewpoint |
4 | Wood sheathing | 0.62 | 22.75 | 9.5 F | 41 F | Below dewpoint |
5 | Air barrier | 0.00 | 22.75 | 9.5 F | 41 F | Below dewpoint |
6 | Siding / cladding | 0.17 | 22.92 | 9.0 F | 41 F | Below dewpoint |
Conclusion: This is the new wall on stories 5 and 6. Layer 3 is the first row below dewpoint. It is the cold plane we protect. Indoor moisture can turn to water if it gets there, and can eventually cause mold. It can get there two ways. It gets there through the drywall, which is why the vapor retarder is on the inside of the wall. It also gets there through holes (outlets, gaps, plates), which is why the air barrier is on the sheathing. Same at the rim.
Existing brick walls (stories 1-4)
# | Layer (inside to outside) | R | Running R | Temp | Dewpoint target | Vs dewpoint |
|---|---|---|---|---|---|---|
1 | Drywall | 1.13 | 1.13 | 67.0 F | 41 F | OK |
2 | R-21 closed-cell spray foam | 21.00 | 22.13 | 11.8 F | 41 F | First below dewpoint |
3 | Wood sheathing | 0.62 | 22.75 | 10.2 F | 41 F | Below dewpoint |
4 | Existing brick | 0.44 | 23.19 | 9.0 F | 41 F | Below dewpoint |
Conclusion: Layer 2 is the first row below dewpoint. It is the cold plane we protect. Indoor moisture can turn to water if it gets there, and can eventually cause mold. An air barrier cannot be installed between the brick and the wood sheathing. R-21 closed-cell spray foam, tight to the sheathing, is the air barrier and the vapor retarder. It does not fill the rest of the 2x6 cavity. Indoor air does not reach the cold sheathing. Same at the rim on stories 1-4.
Roof (sealed attic)
# | Layer (inside to outside) | R | Running R | Temp | Dewpoint target | Vs dewpoint |
|---|---|---|---|---|---|---|
1 | Interior / attic | 0.68 | 0.68 | 68.7 F | 41 F | OK |
2 | Roof deck | 0.62 | 1.30 | 67.5 F | 41 F | OK |
3 | Air barrier | 0.00 | 1.30 | 67.5 F | 41 F | OK |
4 | R-30 continuous insulation | 30.00 | 31.30 | 9.3 F | 41 F | First below dewpoint |
5 | Roofing | 0.17 | 31.47 | 9.0 F | 41 F | Below dewpoint |
Conclusion: Layer 4 is the first row below dewpoint. That plane is outside the deck, in the continuous insulation. The deck stays warm. Indoor moisture can turn to water if it gets to a cold face, and can eventually cause mold. The air barrier is on the deck so room air cannot leak into the insulation.
New walls (stories 5-6) (ELECTRIC)

Existing brick walls (stories 1-4) (ELECTRIC)

Roof (sealed attic) (ELECTRIC)

Rim Joists, stories 5-6 (ELECTRIC)

Path Comparison
This section shows the detailed requirements and incentives for each path we compared, basically showing our work of how we determined the recommended path is the most affordable way of meeting energy code compliance.
Path Comparison - Incentives
CURRENT / ELECTRIC: $36,000 - $90,000
- MassSave Multifamily High Rise Program Base Tier ($36,000) (Program Breakdown): You get this rebate for having your building(s) meet energy code. This requires pre-approval via an application to be submitted before construction starts. This rebate comes in the form of a check within 4 months of certification documentation being provided to MassSave, typically this is 4 months after construction is complete.
- DOER Alternative Energy Credits ($0 - $54,000) (Program Breakdown): This rebate is received for installing APS eligible air source heat pumps (click here for the list). There is an extensive process to get this incentive. It comes in the form of a check approximately 6-12 months after the heat pumps are installed and fully operational.
- IMPORTANT: Although an estimate is provided, this incentive can vary widely typically between $300-1,500 per heat pump. It's based on expected kWh usage of the system as well as the market value of the alternative energy credits when sold.
- Risks: Massachusetts is rewriting this program right now. The House bill would stop the state from accepting new applications on January 1, 2028, the Senate version leaves heat pumps out of that cutoff, and the two are in conference. The application needs the equipment installed and operating, so a project that will not reach that point before the deadline should treat this as upside rather than a budgeted line.
GAS-HEAT: $0
Path Comparison - Net Cost Summary
Path | Total Cost $/sf | Total Incentives $/sf | Net $/sf | OpEx Factor |
|---|---|---|---|---|
ELECTRIC | $50.38 | $1.08 | $49.82 | 1.01 |
GAS-HEAT | $49.97 | $0.00 | $50.58 | 1.01 |
CURRENT | $53.26 | $1.08 | $52.89 | 1.01 |
Path Comparison - Envelope
Item | Path | Detailed Specifications | Cost $/sf | Incentive $/sf | Net $/sf | OpEx |
|---|---|---|---|---|---|---|
Exterior Walls | CURRENT | Existing brick walls (stories 1-4): R-21 closed-cell spray foam against the existing wood sheathing. The foam is the air barrier and the vapor retarder. | $5.14 | $0.00 | $5.14 | 0.95 |
ELECTRIC | Existing brick walls (stories 1-4): R-21 closed-cell spray foam against the existing wood sheathing. The foam is the air barrier and the vapor retarder. | $5.14 | $0.00 | $5.14 | 0.95 | |
GAS-HEAT | Existing brick walls (stories 1-4): R-21 closed-cell spray foam against the existing wood sheathing. The foam is the air barrier and the vapor retarder. | $5.14 | $0.00 | $5.14 | 0.95 | |
Below Grade Walls | CURRENT | N/A | $0.00 | $0.00 | $0.00 | 1.00 |
ELECTRIC | N/A | $0.00 | $0.00 | $0.00 | 1.00 | |
GAS-HEAT | N/A | $0.00 | $0.00 | $0.00 | 1.00 | |
Corridor Walls | CURRENT | N/A | $0.00 | $0.00 | $0.00 | 1.00 |
ELECTRIC | N/A | $0.00 | $0.00 | $0.00 | 1.00 | |
GAS-HEAT | N/A | $0.00 | $0.00 | $0.00 | 1.00 | |
Slab | CURRENT | N/A | $0.00 | $0.00 | $0.00 | 1.00 |
ELECTRIC | N/A | $0.00 | $0.00 | $0.00 | 1.00 | |
GAS-HEAT | N/A | $0.00 | $0.00 | $0.00 | 1.00 | |
Floor Over Unconditioned Space | CURRENT | N/A | $0.00 | $0.00 | $0.00 | 1.00 |
ELECTRIC | N/A | $0.00 | $0.00 | $0.00 | 1.00 | |
GAS-HEAT | N/A | $0.00 | $0.00 | $0.00 | 1.00 | |
Floor Over Garage | CURRENT | N/A | $0.00 | $0.00 | $0.00 | 1.00 |
ELECTRIC | N/A | $0.00 | $0.00 | $0.00 | 1.00 | |
GAS-HEAT | N/A | $0.00 | $0.00 | $0.00 | 1.00 | |
Floor Over Podium | CURRENT | N/A | $0.00 | $0.00 | $0.00 | 1.00 |
ELECTRIC | N/A | $0.00 | $0.00 | $0.00 | 1.00 | |
GAS-HEAT | N/A | $0.00 | $0.00 | $0.00 | 1.00 | |
Rim Joists | CURRENT | Stories 1-4: R-21 closed-cell spray foam at the rim band, tight to the sheathing. The foam is the air barrier. | $0.20 | $0.00 | $0.20 | 0.95 |
ELECTRIC | Stories 1-4: R-21 closed-cell spray foam at the rim band, tight to the sheathing. The foam is the air barrier. | $0.20 | $0.00 | $0.20 | 0.95 | |
GAS-HEAT | Stories 1-4: R-21 closed-cell spray foam at the rim band, tight to the sheathing. The foam is the air barrier. | $0.20 | $0.00 | $0.20 | 0.95 | |
Roof | CURRENT | Sealed attic: ≥ R-30 continuous insulation. | $1.21 | $0.00 | $1.21 | 1.10 |
ELECTRIC | Sealed attic: ≥ R-30 continuous insulation. | $1.21 | $0.00 | $1.21 | 1.10 | |
GAS-HEAT | Sealed attic: ≥ R-30 continuous insulation. | $1.21 | $0.00 | $1.21 | 1.10 | |
Windows & Glass Doors | CURRENT | Double pane, U ≤ 0.30 / SHGC 0.30-0.40. | $5.89 | $0.00 | $5.89 | 1.00 |
ELECTRIC | Double pane, U ≤ 0.30 / SHGC 0.30-0.40. | $5.89 | $0.00 | $5.89 | 1.00 | |
GAS-HEAT | Double pane, U ≤ 0.30 / SHGC 0.30-0.40. | $5.89 | $0.00 | $5.89 | 1.00 | |
Doors | CURRENT | Opaque door, U ≤ 0.20 (R-5.0). | $0.35 | $0.00 | $0.35 | 0.95 |
ELECTRIC | Opaque door, U ≤ 0.20 (R-5.0). | $0.35 | $0.00 | $0.35 | 0.95 | |
GAS-HEAT | Opaque door, U ≤ 0.20 (R-5.0). | $0.35 | $0.00 | $0.35 | 0.95 | |
Air Sealing | CURRENT | ≤ 0.30 CFM50 per sqft of enclosure (compartmentalization); tested. | $1.20 | $0.00 | $1.20 | 0.95 |
ELECTRIC | ≤ 0.30 CFM50 per sqft of enclosure (compartmentalization); tested. | $1.20 | $0.00 | $1.20 | 0.95 | |
GAS-HEAT | ≤ 0.30 CFM50 per sqft of enclosure (compartmentalization); tested. | $1.20 | $0.00 | $1.20 | 0.95 |
Path Comparison - Mechanical
Item | Path | Detailed Specifications | Cost $/sf | Incentive $/sf | Net $/sf | OpEx |
|---|---|---|---|---|---|---|
HVAC | CURRENT | Ducted air-source heat pump; SEER2 ≥ 16; HSPF2 ≥ 8.5. See HVAC Design Loads. | $14.26 | $0.00 | $14.26 | 1.15 |
ELECTRIC | Ducted air-source heat pump; SEER2 ≥ 16; HSPF2 ≥ 8.5. See HVAC Design Loads. | $14.26 | $0.00 | $14.26 | 1.15 | |
GAS-HEAT | Natural gas furnace; AFUE ≥ 85; cooling by a separate system, cooling only; SEER2 ≥ 16. See HVAC Design Loads. | $10.97 | $0.00 | $10.97 | 1.10 | |
Ductwork | CURRENT | Supply and return ducts in conditioned space insulated to code minimum. | $5.21 | $0.00 | $5.21 | 1.00 |
ELECTRIC | Supply and return ducts in conditioned space insulated to code minimum. | $5.21 | $0.00 | $5.21 | 1.00 | |
GAS-HEAT | Supply and return ducts in conditioned space insulated to code minimum. | $5.21 | $0.00 | $5.21 | 1.00 | |
Duct Sealing | CURRENT | ≤ greater of 80 CFM25 or 8 CFM25 per 100 sqft of conditioned floor area; tested at final. | $0.89 | $0.00 | $0.89 | 1.00 |
ELECTRIC | ≤ greater of 80 CFM25 or 8 CFM25 per 100 sqft of conditioned floor area; tested at final. | $0.89 | $0.00 | $0.89 | 1.00 | |
GAS-HEAT | ≤ greater of 80 CFM25 or 8 CFM25 per 100 sqft of conditioned floor area; tested at final. | $0.89 | $0.00 | $0.89 | 1.00 | |
HVAC Grading | CURRENT | Fan Flow Test: Grade II | $0.00 | $0.00 | $0.00 | 1.00 |
ELECTRIC | Fan Flow Test: Grade II | $0.00 | $0.00 | $0.00 | 1.00 | |
GAS-HEAT | Fan Flow Test: Grade II | $0.00 | $0.00 | $0.00 | 1.00 | |
Mechanical Ventilation | CURRENT | In-unit ERV | $1.62 | $0.00 | $1.62 | 1.20 |
ELECTRIC | In-unit ERV | $1.62 | $0.00 | $1.62 | 1.20 | |
GAS-HEAT | In-unit ERV | $1.62 | $0.00 | $1.62 | 1.20 | |
Local Mechanical Exhaust | CURRENT | Bathroom(s): at least 50 CFM intermittent and up to 3.0 sones, or at least 20 CFM continuous and up to 2.0 sones. | $1.27 | $0.00 | $1.27 | 1.05 |
ELECTRIC | Bathroom(s): at least 50 CFM intermittent and up to 3.0 sones, or at least 20 CFM continuous and up to 2.0 sones. | $1.27 | $0.00 | $1.27 | 1.05 | |
GAS-HEAT | Bathroom(s): at least 50 CFM intermittent and up to 3.0 sones, or at least 20 CFM continuous and up to 2.0 sones. | $1.27 | $0.00 | $1.27 | 1.05 | |
Thermostats | CURRENT | Programmable thermostat. | $0.15 | $0.00 | $0.15 | 1.05 |
ELECTRIC | Programmable thermostat. | $0.15 | $0.00 | $0.15 | 1.05 | |
GAS-HEAT | Programmable thermostat. | $0.15 | $0.00 | $0.15 | 1.05 |
Path Comparison - Plumbing & Appliances
Item | Path | Detailed Specifications | Cost $/sf | Incentive $/sf | Net $/sf | OpEx |
|---|---|---|---|---|---|---|
DHW | CURRENT | Centralized gas water heating system with two 100 gallon tanks and a temperature-controlled recirculating system; ≥ 0.80 energy factor. | $3.96 | $0.00 | $3.96 | 1.00 |
ELECTRIC | Electric resistance storage water heater; UEF ≥ 0.92; 50 gal. | $1.08 | $0.00 | $1.08 | 0.90 | |
GAS-HEAT | Centralized gas water heating system with two 100 gallon tanks and a temperature-controlled recirculating system; ≥ 0.85 energy factor. | $3.96 | $0.00 | $3.96 | 1.00 | |
DHW Piping | CURRENT | Supply piping insulated to ≥ R-3. | $0.89 | $0.00 | $0.89 | 0.95 |
ELECTRIC | Supply piping insulated to ≥ R-3. | $0.89 | $0.00 | $0.89 | 0.95 | |
GAS-HEAT | Supply piping insulated to ≥ R-3. | $0.89 | $0.00 | $0.89 | 0.95 | |
Water Fixtures | CURRENT | WaterSense certified (Lavatory ≤ 1.2 GPM; Shower ≤ 2.0 GPM; Kitchen ≤ 2.2 GPM). | $2.23 | $0.00 | $2.23 | 1.00 |
ELECTRIC | WaterSense certified (Lavatory ≤ 1.2 GPM; Shower ≤ 2.0 GPM; Kitchen ≤ 2.2 GPM). | $2.23 | $0.00 | $2.23 | 1.00 | |
GAS-HEAT | WaterSense certified (Lavatory ≤ 1.2 GPM; Shower ≤ 2.0 GPM; Kitchen ≤ 2.2 GPM). | $2.23 | $0.00 | $2.23 | 1.00 | |
Refrigerator | CURRENT | ≤ 650 kWh/yr; electric. | $0.92 | $0.00 | $0.92 | 1.10 |
ELECTRIC | ≤ 650 kWh/yr; electric. | $0.92 | $0.00 | $0.92 | 1.10 | |
GAS-HEAT | ≤ 650 kWh/yr; electric. | $0.92 | $0.00 | $0.92 | 1.10 | |
Dishwasher | CURRENT | ≤ 269 kWh/yr; electric. | $0.52 | $0.00 | $0.52 | 1.10 |
ELECTRIC | ≤ 269 kWh/yr; electric. | $0.52 | $0.00 | $0.52 | 1.10 | |
GAS-HEAT | ≤ 269 kWh/yr; electric. | $0.52 | $0.00 | $0.52 | 1.10 | |
Clothes Washer | CURRENT | IMEF ≥ 2.06; IWF ≤ 4.2; ≤ 152 kWh/yr; electric. | $0.60 | $0.00 | $0.60 | 1.10 |
ELECTRIC | IMEF ≥ 2.06; IWF ≤ 4.2; ≤ 152 kWh/yr; electric. | $0.60 | $0.00 | $0.60 | 1.10 | |
GAS-HEAT | IMEF ≥ 2.06; IWF ≤ 4.2; ≤ 152 kWh/yr; electric. | $0.60 | $0.00 | $0.60 | 1.10 | |
Clothes Dryer | CURRENT | Standard electric dryer; vented; CEF ≥ 3.93. | $0.67 | $0.00 | $0.67 | 1.00 |
ELECTRIC | Standard electric dryer; vented; CEF ≥ 3.93. | $0.67 | $0.00 | $0.67 | 1.00 | |
GAS-HEAT | Standard electric dryer; vented; CEF ≥ 3.93. | $0.67 | $0.00 | $0.67 | 1.00 | |
Stove / Oven | CURRENT | Electric range. | $0.71 | $0.00 | $0.71 | 1.00 |
ELECTRIC | Electric range. | $0.71 | $0.00 | $0.71 | 1.00 | |
GAS-HEAT | Electric range. | $0.71 | $0.00 | $0.71 | 1.00 |
Path Comparison - Electrical
Item | Path | Detailed Specifications | Cost $/sf | Incentive $/sf | Net $/sf | OpEx |
|---|---|---|---|---|---|---|
Lighting | CURRENT | ≥ 100% high-efficacy (LED). | $4.00 | $0.00 | $4.00 | 0.85 |
ELECTRIC | ≥ 100% high-efficacy (LED). | $4.00 | $0.00 | $4.00 | 0.85 | |
GAS-HEAT | ≥ 100% high-efficacy (LED). | $4.00 | $0.00 | $4.00 | 0.85 | |
Solar Ready | CURRENT | A solar system will be installed, so solar-ready requirements are exempt. | $0.00 | $0.00 | $0.00 | 1.00 |
ELECTRIC | A solar system will be installed, so solar-ready requirements are exempt. | $0.00 | $0.00 | $0.00 | 1.00 | |
GAS-HEAT | A solar system will be installed, so solar-ready requirements are exempt. | $0.00 | $0.00 | $0.00 | 1.00 | |
EV Ready | CURRENT | 20% of parking spaces EV-ready. | $0.46 | $0.00 | $0.46 | 1.00 |
ELECTRIC | 20% of parking spaces EV-ready. | $0.46 | $0.00 | $0.46 | 1.00 | |
GAS-HEAT | 20% of parking spaces EV-ready. | $0.46 | $0.00 | $0.46 | 1.00 | |
HPWH Ready | CURRENT | N/A | $0.00 | $0.00 | $0.00 | 1.00 |
ELECTRIC | N/A | $0.00 | $0.00 | $0.00 | 1.00 | |
GAS-HEAT | N/A | $0.00 | $0.00 | $0.00 | 1.00 |
Path Comparison - Soft Costs & Whole-Building Incentives
Item | Path | Detailed Specifications | Cost $/sf | Incentive $/sf | Net $/sf | OpEx |
|---|---|---|---|---|---|---|
Paperwork & Modeling | CURRENT | ENERGY STAR energy model to the target (per-unit HERS or whole-building ASHRAE path), the ENERGY STAR design-review checklist and multifamily workbook, and an HVAC design report. | $0.27 | $1.08 | -$0.81 | 1.00 |
ELECTRIC | ENERGY STAR energy model to the target (per-unit HERS or whole-building ASHRAE path), the ENERGY STAR design-review checklist and multifamily workbook, and an HVAC design report. | $0.27 | $1.08 | -$0.81 | 1.00 | |
GAS-HEAT | ENERGY STAR energy model to the target (per-unit HERS or whole-building ASHRAE path), the ENERGY STAR design-review checklist and multifamily workbook, and an HVAC design report. | $0.27 | $0.00 | $0.27 | 1.00 | |
Testing & Verification | CURRENT | ENERGY STAR field verification: pre-drywall and final inspections, unit air-tightness (blower door), duct-leakage, ventilation and exhaust airflow, and HVAC functional testing. | $0.64 | $0.00 | $0.64 | 1.00 |
ELECTRIC | ENERGY STAR field verification: pre-drywall and final inspections, unit air-tightness (blower door), duct-leakage, ventilation and exhaust airflow, and HVAC functional testing. | $0.64 | $0.00 | $0.64 | 1.00 | |
GAS-HEAT | ENERGY STAR field verification: pre-drywall and final inspections, unit air-tightness (blower door), duct-leakage, ventilation and exhaust airflow, and HVAC functional testing. | $0.64 | $0.00 | $0.64 | 1.00 |
Additional Design Considerations Not Represented In This Study
- Smaller Heat Pumps on the CURRENT and ELECTRIC Units: A smaller heat pump sized to the cooling load was not used on the CURRENT and ELECTRIC two- and three-bedroom units, because heating set the size. Both paths keep single-stage ducted heat pumps at 24 kBtuh on the two-bedroom, 183.2 percent of the 13.1 kBtuh ELECTRIC cooling load and 184.6 percent of the 13.0 kBtuh CURRENT load, and 30 kBtuh on the three-bedroom, 164.8 percent of the 18.2 kBtuh load. ENERGY STAR MFNC holds a single-stage unit to 130 percent of the cooling load, or to 20 kBtuh when the cooling load is 15 kBtuh or less, and both sizes sit above that limit. The same units cover the design heating load, 21.1 kBtuh against 19.6 kBtuh on ELECTRIC and 19.3 kBtuh on CURRENT for the two-bedroom, and 26.4 kBtuh against 22.3 kBtuh for the three-bedroom. A two-stage or variable-speed unit at the same 24 kBtuh may go to 25 kBtuh when the cooling load is 18 kBtuh or less, which would clear the two-bedroom limit, and that equipment is not in this study. The three-bedroom cooling load is 18.2 kBtuh, so that allowance does not apply, and 30 kBtuh is also above the 160 percent variable-speed ceiling. GAS-HEAT passes both the cooling and heating sizing gates with a separate 12 kBtuh and 18 kBtuh cooling system.