Recommended Path
Path 2 - Remove Continuous Insulation

Goal

To find the most cost-effective compliance path, this report isolates energy code related costs from total construction. We use real bid data from vendors & clients to create a reliable framework for aligning incentives and design, with all recommendations confirmed by detailed energy modeling.

Project

  • Westford, MA 01886
  • 530 Units | 513,871 sqft
  • New Construction | Multifamily Luxury Apartments
  • All-Electric | Stretch Code | HERS ≤ 45 | ESTAR MFNC v1.2

Overview

Read This: This report compares different ways you can build the project and meet energy code, looking at both cost and incentives, with the ultimate goal as finding the most affordable path.

  • The overview outlines the key differences between each of the paths we show in this report and why we recommend the one we picked over the others.
  • The recommended design section is where we share the requirements and incentives for the path we think is best based on affordability.
  • The path comparison section shows the detailed requirements and incentives for each path we compared, basically showing our work if you want to dig in.

Path Summary

Path 1 - Change Nothing: The 50% Permit Progress Set as drawn, R-21 mineral wool batt + 3 inches of continuous mineral wool (R-12.6 CI) on a thermally-broken Z-girt rainscreen, Intus Supera CW70 triple-pane tilt-turn casement windows (U-0.17, SHGC-0.32), Daikin Aurora ducted cold-climate heat pumps in each unit, 50/65-gallon heat pump water heaters in the AHU/HWH closet, and Panasonic Intelli-Balance ERVs. Worst-case unit modeled at HERS 42.00 (B4-ML-EXT, 2BR corner middle floor) with a 3.0-point buffer to the HERS 45 binding target; total construction cost approximately $48.01/sf NRSF, or roughly $24.4M across the residential project. By overinvesting in continuous insulation and triple-pane glazing beyond what TEDI compliance requires, Path A wastes approximately $677,000 versus Path B and approximately $3,994,000 versus Path C, both alternative paths still pass HERS 45 with margin.

Path 2 - Remove Continuous Insulation (Recommended): Path B removes the 3 inches of continuous mineral wool and the Z-girt rainscreen, replacing the wall thermal package with R-30 split closed-cell + open-cell spray foam in the 2x6 cavity (3 inches of closed cell against the sheathing for air seal and Class II vapor retarder, plus 2.5 inches of open cell for sound dampening and full cavity fill). Cladding installs directly over the OSB sheathing with standard furring instead of the thermally-broken Z-girt system, and spray foam serves dual duty as cavity insulation and air barrier simplifying construction sequencing and reducing trade coordination. The Intus Supera CW70 triple-pane window package is retained for luxury aesthetic and lease-up positioning, HPWH water heating is retained (preserving the $132,500 MassSave HPWH adder), and all three MassSave incentives totaling $1,113,000 stay intact. Worst-case HERS 42.30 with a 2.7-point buffer; Path B saves approximately $677,000 versus Path A while keeping every visible quality element of the original design.

Path 3 - Remove Continuous Insulation & Triple Pane Windows (Great Alternative): Path C combines the wall change from Path B with a window downgrade from triple-pane Intus Supera CW70 to mid-tier double-pane low-E argon-filled vinyl (U-0.27, SHGC-0.40), capturing the biggest single cost lever in the project. Total savings are approximately $3,994,000 versus Path A and approximately $3,317,000 versus Path B; appropriate when the client prioritizes capital cost reduction over premium window aesthetic, since double-pane still meets ENERGY STAR window requirements for the climate zone. The trade-off is a tight 0.4-point buffer (worst-case HERS 44.59), leaving limited margin for as-built deviations in air sealing, HVAC commissioning, or material substitution; combined with the OS-ERI to Ekotrope +/- 2 HERS calibration tolerance, Phase 3 final verification could land anywhere from HERS 42.6 to 46.6 on the worst-case unit. The lease-up team should also weigh whether the cost savings justify the loss of the European tilt-turn casement aesthetic the architect specified.

Code Summary

The project is multiple 5-story multifamily apartment buildings (Group R), classified under Massachusetts 225 CMR Chapter 23 (commercial energy code) because of the building height. The design team selected the Targeted Performance compliance path, more commonly known as TEDI (Thermal Energy Demand Intensity), which sets an absolute energy use target for the whole building under the MA 2023 Stretch Code.

ECC evaluated the project through the standard ANSI/RESNET/ICC 301-2022 Energy Rating Index (ERI) methodology in parallel. The ERI rating supports ENERGY STAR Multifamily New Construction (MFNC) v1.2 certification (which carries the $927,500 MassSave rebate) and qualifies each unit type for the MassSave Multifamily High Rise program.

Code Path

Code Path Table Code Path

Code Requirements

Code Requirements

Recommended Design - Incentives

Incentives Available: $1,113,000

  • MassSave Multifamily High Rise Program Energy Star Tier ($927,500): You get this rebate for having your building(s) certified for the Energy Star MFNC v1.2 program. This requires pre-approval via an application to be submitted before construction starts. This rebate comes in the form of a check within 4 months of certification documentation being provided to MassSave, typically this is 4 months after construction is complete. (Program Breakdown)
  • MassSave Multifamily Heat Pump Water Heater Adder ($132,500): You get this rebate for installing heat pump water heaters in your units. This requires pre-approval via an application to be submitted before construction starts. This rebate comes in the form of a check within 4 months of certification documentation being provided to MassSave, typically this is 4 months after construction is complete. (Program Breakdown)
  • MassSave Multifamily Wifi Enabled Thermostat Adder ($53,000): You get this rebate for installing wifi enabled thermostats in your units. This requires pre-approval via an application to be submitted before construction starts. This rebate comes in the form of a check within 4 months of certification documentation being provided to MassSave, typically this is 4 months after construction is complete. (Program Breakdown)

Recommended Design - Units

ItemDetailed Specifications
Exterior Walls2x6 wood @ 16" OC; R-30 split closed/open cell spray foam in cavity (3" ccSPF + 2.5" ocSPF), no continuous insulation; cladding direct on sheathing
SlabSlab on grade (conditioned units only); 4" concrete; R-10 XPS underslab; 20-mil vapor barrier; thermal break at perimeter
Rim JoistsWood rim board / LSL; 3" closed-cell spray foam (R-21) in rim cavity; no CI
RoofAbove-deck insulation flat roof: wood truss + R-50 rigid polyiso (10" min, 2+ staggered layers, continuous over deck)
Windows & Glass DoorsTriple-pane tilt-turn casement; U-0.17 / SHGC-0.32
DoorsGlazed balcony swing doors with sidelite (matches window thermal performance, U-0.20); insulated opaque unit-entry door R-4.75 to conditioned corridor (Product Rec)
Air SealingTested ≤ 0.30 CFM50 / sf shell area; blower-door tested at final per RESNET (Air Sealing Protocol).
HVACDucted cold-climate air-source heat pump per unit; sizing 18 / 24 / 30 kBTU by unit type (studios/1BR / 2BR / 3BR); SEER2 16.0-17.5 / HSPF2 8.8-9.0; ENERGY STAR CCHP; R-32 refrigerant; horizontal air handler in in-unit closet
DuctworkSupply / return ducts in conditioned space (in-unit closet + ceiling chase); R-6 insulation
Duct Sealing & TestDuct total leakage tested: The greater of ≤ 80 CFM50 OR ≤ 8 CFM/100sf floor area (per RESNET 380) (Duct Sealing Protocol).
HVAC GradingFan Flow Test: Grade 1
Watt Draw Test: Grade 1
Refrigerant Charge: Grade 1/3
Mechanical VentilationERV per unit; sized per ASHRAE 62.2 (30 CFM studios+1BR / 60 CFM 2BR+3BR); 78-85% sensible recovery efficiency at design CFM; 12W; cold-climate rated; in-unit closet (Product Rec)
Local Mechanical ExhaustBathroom(s): ≥50 CFM intermittent & ≤3.0 sones OR ≥20 CFM continuous & ≤2.0 sones. Kitchen(s): ≥100 CFM intermittent & ≤3.0 sones OR continuous, ≥5 ACH. Both: Exhaust directly outdoors, ENERGY STAR certified, utilize ERV.
ThermostatsWiFi-enabled programmable smart thermostat per zone; integrated with utility demand-response program
DHWHeat pump water heater per unit; UEF 4.07 (50 gal, 0-2BR) / UEF 3.88 (65 gal, 3BR); 240V/30A; in corridor closet
DHW PipingR-3 pipe insulation on all hot water lines; Hot Water Max Pipe Run Targets = 1/2 of refPipeL formula 2·√(CFA/Nfl) + 10·Nfl at largest CFA in each tier, plus 5 ft for corridor-to-unit run
Water FixturesWaterSense certified low-flow: lavatory ≤1.5 gpm; shower ≤1.8 gpm; kitchen sink ≤1.8 gpm
RefrigeratorENERGY STAR certified; 31 cu ft French door (645 kWh/yr) standard / 25 cu ft side-by-side (600 kWh/yr) ADA Group 2 units
DishwasherENERGY STAR certified; 240 kWh/yr; standard efficiency; 12 place settings
Clothes WasherFront-load; ENERGY STAR; IMEF 2.76 / IWF 3.2; 4.3 cu ft; 123 kWh/yr; closet-depth fit
Clothes DryerElectric vented (long-vent stacked); ENERGY STAR; CEF 3.93; 7.4 cu ft
Stove / OvenElectric glass cooktop, freestanding range; non-induction; ADA Group 2 units use separate wall oven + cooktop
Lighting100% LED
Solar ReadyDesignated Solar Zone: Reserve a contiguous area equal to at least 40% of the total horizontal roof area. Contiguity: Zone free of obstructions, minimum 5 ft wide. Structural Capacity: 5 PSF collateral dead load. Electrical Infrastructure: Conduit pathways and reserved breaker space.
EV ReadyEV Ready infrastructure for at least 20% of total parking. Branch circuit and termination for required spaces, rated for at least 6.2 kVA per space.
Paperwork & ModelingHERS/ERI energy model, 2021 IECC checklists, ENERGY STAR checklists, incentive documentation.
Testing & VerificationUnit Blower Door Test, Mechanical Ventilation Testing, Room Balancing, Predrywall & Final Inspection.

Recommended Design - Common Space

ItemDetailed Specifications
Exterior WallsR-30 ccSPF in 2x6 cavity @ 16 oc; ZIP sheathing
Below-Grade WallsR-7.5 CI
SlabR-10 XPS perimeter 4 ft
Rim JoistsSeal interior rim cavity with minimum 3" closed-cell spray foam
RoofSealed (unvented) flat roof; R-49 ccSPF + ocSPF assembly
WindowsFixed: U-0.36 / SHGC 0.40; Operable: U-0.43 / SHGC 0.40
DoorsEntrance: U-0.77 / SHGC 0.40; Opaque: U-0.61
Air SealingWhole-building air barrier per 2024 IECC C402.5. Materials-based compliance (assemblies ≤0.04 cfm/ft² per ASTM E2357) or whole-building pressurization testing (≤0.27 CFM50/ft² at 50 Pa).
HVACDucted split heat pump; SEER2 ≥15.2 / HSPF2 ≥7.8 / EER2 ≥11.7; ENERGY STAR certified; sized per Manual J/S, ≤15% above calculated cooling load.
Duct Sealing≤8 CFM25 per 100 ft² CFA or 80 CFM, whichever is greater.
Mechanical VentilationPer ASHRAE 62.1: Lobby/Office 5 cfm/person + 0.06 cfm/ft²; Fitness 20 cfm/person + 0.18 cfm/ft²; Corridor 0.06 cfm/ft²; Laundry 5 cfm/person + 0.12 cfm/ft². ERV required if total OA intake ≥1,000 cfm. Demand controlled ventilation required for spaces >500 ft² with occupancy >25 people per 1,000 ft².
Local Mechanical ExhaustPer ASHRAE 62.1 exhaust rates. Common restrooms, laundry, mechanical rooms as applicable.
ThermostatsProgrammable with 5°F setback capability during unoccupied periods.
DHWPoint-of-use electric water heater for common restroom sinks (if applicable).
DHW PipingPiping insulated to R-3 (≤1.5" pipe) / R-4 (>1.5" pipe).
Water FixturesWaterSense certified: Lavatory ≤1.5 GPM; Toilet ≤1.28 GPF; Urinal (if installed) ≤0.5 GPF.
Lighting100% LED. LPD limits by space: Corridor 0.41 W/ft²; Lobby 0.84; Office 0.74; Fitness 0.63; Community Room 0.59; Laundry 0.53; Stairway 0.49; Mechanical/Electrical 0.43; Storage 0.38.
Lighting ControlsOccupancy/vacancy sensors in all common spaces (corridors/stairs may dim to 50% instead of off). Daylight responsive controls where daylighted area >150 ft². Automatic time switches on all common area lighting.
Solar ReadyPer dwelling unit table (building-wide requirement).
EV ReadyPer dwelling unit table (building-wide requirement).
Paperwork & ModelingCOMcheck report for common areas, ASHRAE 62.1 ventilation calcs, lighting power density calcs.
Testing & VerificationMechanical ventilation balancing, lighting controls commissioning, rough-in and final inspection.

Exterior Wall Assembly (Recommended Path)

Exterior Wall Assembly

Rim Joist (Recommended Path)

Rim Joist Assembly

Roof (Recommended Path)

Roof Assembly

Slab Edge (Recommended Path)

Slab Edge Assembly

Path Comparison - Incentives

All Paths: $1,113,000

  • MassSave Multifamily High Rise Program Energy Star Tier ($927,500): You get this rebate for having your building(s) certified for the Energy Star MFNC v1.2 program. This requires pre-approval via an application to be submitted before construction starts. This rebate comes in the form of a check within 4 months of certification documentation being provided to MassSave, typically this is 4 months after construction is complete. (Program Breakdown)
  • MassSave Multifamily Heat Pump Water Heater Adder ($132,500): You get this rebate for installing heat pump water heaters in your units. This requires pre-approval via an application to be submitted before construction starts. This rebate comes in the form of a check within 4 months of certification documentation being provided to MassSave, typically this is 4 months after construction is complete. (Program Breakdown)
  • MassSave Multifamily Wifi Enabled Thermostat Adder ($53,000): You get this rebate for installing wifi enabled thermostats in your units. This requires pre-approval via an application to be submitted before construction starts. This rebate comes in the form of a check within 4 months of certification documentation being provided to MassSave, typically this is 4 months after construction is complete. (Program Breakdown)

Path Comparison - Net Cost Summary

PathTotal Cost $/sfTotal Incentives $/sfNet $/sfOpEx FactorWorst HERS$/HERS Point
Path 1$48.01$2.19$45.820.9842.00$1.09
Path 2 (Recommended)$46.68$2.19$44.490.9842.30$1.05
Path 3$40.16$2.19$37.970.9844.59$0.85

Path Comparison - Envelope

ItemPathDetailed SpecificationsCost $/sfIncentive $/sfNet $/sfOpEx Factor
Exterior WallsPath 12x6 wood @ 16" OC; R-21 mineral wool batt cavity; R-12.6 CI continuous (3" mineral wool, thermally-broken Z-girt rainscreen); fiber cement / brick cladding on rainscreen$5.98$0.00$5.980.85
Exterior WallsPath 22x6 wood @ 16" OC; R-30 split closed/open cell spray foam in cavity (3" ccSPF + 2.5" ocSPF), no continuous insulation; cladding direct on sheathing with standard furring$4.67$0.00$4.670.85
Exterior WallsPath 3Same as Path 2 (R-30 SPF cavity, no CI)$4.67$0.00$4.670.85
SlabPath 1Slab on grade (conditioned units only); 4" concrete; R-10 XPS underslab; 20-mil vapor barrier; thermal break at perimeter$1.40$0.00$1.400.90
SlabPath 2Same as Path 1$1.40$0.00$1.400.90
SlabPath 3Same as Path 1$1.40$0.00$1.400.90
Rim JoistsPath 1Wood rim board / LSL; R-12.6 CI continuous (matches wall CI)$0.20$0.00$0.200.85
Rim JoistsPath 2Wood rim board / LSL; 3" closed-cell spray foam (R-21) in rim cavity; no CI$0.18$0.00$0.180.85
Rim JoistsPath 3Same as Path 2$0.18$0.00$0.180.85
RoofPath 1Above-deck insulation flat roof: wood truss + R-50 rigid polyiso (10" min, 2+ staggered layers, continuous over deck)$5.20$0.00$5.200.95
RoofPath 2Same as Path 1$5.20$0.00$5.200.95
RoofPath 3Same as Path 1$5.20$0.00$5.200.95
Windows & Glass DoorsPath 1Triple-pane tilt-turn casement; U-0.17 / SHGC-0.32; ENERGY STAR certified; black frame; passive-house grade$11.23$0.00$11.230.95
Windows & Glass DoorsPath 2Same as Path 1$11.23$0.00$11.230.95
Windows & Glass DoorsPath 3Double-pane low-E argon-filled vinyl; U-0.27 / SHGC-0.40; ENERGY STAR certified$4.91$0.00$4.911.00
DoorsPath 1Insulated opaque unit-entry door R-4.75 to conditioned corridor$0.50$0.00$0.501.00
DoorsPath 2Same as Path 1$0.50$0.00$0.501.00
DoorsPath 3Insulated opaque unit-entry door R-4.75 to conditioned corridor$0.30$0.00$0.301.00
Air SealingPath 1Tested ≤ 0.30 CFM50 / sf shell area; blower-door tested at final per RESNET (Air Sealing Protocol).$0.40$0.00$0.400.85
Air SealingPath 2Same as Path 1 (Air Sealing Protocol).$0.40$0.00$0.400.85
Air SealingPath 3Same as Path 1 (Air Sealing Protocol).$0.40$0.00$0.400.85

Path Comparison - Mechanical

ItemPathDetailed SpecificationsCost $/sfIncentive $/sfNet $/sfOpEx Factor
HVACPath 1Ducted cold-climate air-source heat pump per unit; sizing 18 / 24 / 30 kBTU by unit type (studios/1BR / 2BR / 3BR); SEER2 16.0-17.5 / HSPF2 8.8-9.0; ENERGY STAR CCHP; R-32 refrigerant; horizontal air handler in in-unit closet$9.50$0.00$9.501.05
HVACPath 2Same as Path 1$9.50$0.00$9.501.05
HVACPath 3Same as Path 1$9.50$0.00$9.501.05
DuctworkPath 1Supply / return ducts in conditioned space (in-unit closet + ceiling chase); R-6 insulation$2.80$0.00$2.801.05
DuctworkPath 2Same as Path 1$2.80$0.00$2.801.05
DuctworkPath 3Same as Path 1$2.80$0.00$2.801.05
Duct Sealing & TestPath 1Duct total leakage tested: The greater of ≤ 80 CFM50 OR ≤ 8 CFM/100sf floor area (per RESNET 380) (Duct Sealing Protocol).$0.30$0.00$0.301.00
Duct Sealing & TestPath 2Same as Path 1 (Duct Sealing Protocol).$0.30$0.00$0.301.00
Duct Sealing & TestPath 3Same as Path 1 (Duct Sealing Protocol).$0.30$0.00$0.301.00
HVAC GradingPath 1Fan Flow Test: Grade 1; Watt Draw Test: Grade 1; Refrigerant Charge: Grade 1/3$0.30$0.00$0.301.00
HVAC GradingPath 2Same as Path 1$0.30$0.00$0.301.00
HVAC GradingPath 3Same as Path 1$0.30$0.00$0.301.00
Mechanical VentilationPath 1ERV per unit; sized per ASHRAE 62.2 (30 CFM studios+1BR / 60 CFM 2BR+3BR); 78-85% sensible recovery efficiency at design CFM; 12W; cold-climate rated; in-unit closet$1.20$0.00$1.201.05
Mechanical VentilationPath 2Same as Path 1$1.20$0.00$1.201.05
Mechanical VentilationPath 3Same as Path 1$1.20$0.00$1.201.05
Local Mechanical ExhaustPath 1Bathroom(s): ≥50 CFM intermittent & ≤3.0 sones OR ≥20 CFM continuous & ≤2.0 sones. Kitchen(s): ≥100 CFM intermittent & ≤3.0 sones OR continuous, ≥5 ACH. Both: Exhaust directly outdoors, ENERGY STAR certified, utilize ERV.$0.30$0.00$0.301.00
Local Mechanical ExhaustPath 2Same as Path 1$0.30$0.00$0.301.00
Local Mechanical ExhaustPath 3Same as Path 1$0.30$0.00$0.301.00
ThermostatsPath 1WiFi-enabled programmable smart thermostat per zone; integrated with utility demand-response program$0.20$0.10$0.101.00
ThermostatsPath 2Same as Path 1$0.20$0.10$0.101.00
ThermostatsPath 3Same as Path 1$0.20$0.10$0.101.00

Path Comparison - Plumbing & Appliances

ItemPathDetailed SpecificationsCost $/sfIncentive $/sfNet $/sfOpEx Factor
DHWPath 1Heat pump water heater per unit; UEF 4.07 (50 gal, 0-2BR) / UEF 3.88 (65 gal, 3BR); 240V/30A; in corridor closet$4.20$0.26$3.941.20
DHWPath 2Same as Path 1$4.20$0.26$3.941.20
DHWPath 3Same as Path 1$4.20$0.26$3.941.20
DHW PipingPath 1R-3 pipe insulation on all hot water lines. Hot Water Max Pipe Run Targets = 1/2 of refPipeL formula 2·√(CFA/Nfl) + 10·Nfl at largest CFA in each tier, plus 5 ft for corridor-to-unit run.$0.80$0.00$0.801.00
DHW PipingPath 2Same as Path 1$0.80$0.00$0.801.00
DHW PipingPath 3Same as Path 1$0.80$0.00$0.801.00
Water FixturesPath 1WaterSense certified low-flow: lavatory ≤1.5 gpm; shower ≤1.8 gpm; kitchen sink ≤1.8 gpm$0.80$0.00$0.800.95
Water FixturesPath 2Same as Path 1$0.80$0.00$0.800.95
Water FixturesPath 3Same as Path 1$0.80$0.00$0.800.95
RefrigeratorPath 1ENERGY STAR certified; 31 cu ft French door (645 kWh/yr) standard / 25 cu ft side-by-side (600 kWh/yr) ADA Group 2 units$0.30$0.00$0.301.00
RefrigeratorPath 2Same as Path 1$0.30$0.00$0.301.00
RefrigeratorPath 3Same as Path 1$0.30$0.00$0.301.00
DishwasherPath 1ENERGY STAR certified; 240 kWh/yr; standard efficiency; 12 place settings$0.20$0.00$0.201.00
DishwasherPath 2Same as Path 1$0.20$0.00$0.201.00
DishwasherPath 3Same as Path 1$0.20$0.00$0.201.00
Clothes WasherPath 1Front-load; ENERGY STAR; IMEF 2.76 / IWF 3.2; 4.3 cu ft; 123 kWh/yr; closet-depth fit$0.40$0.00$0.401.00
Clothes WasherPath 2Same as Path 1$0.40$0.00$0.401.00
Clothes WasherPath 3Same as Path 1$0.40$0.00$0.401.00
Clothes DryerPath 1Electric vented (long-vent stacked); ENERGY STAR; CEF 3.93; 7.4 cu ft$0.35$0.00$0.351.00
Clothes DryerPath 2Same as Path 1$0.35$0.00$0.351.00
Clothes DryerPath 3Same as Path 1$0.35$0.00$0.351.00
Stove / OvenPath 1Electric glass cooktop, freestanding range; non-induction; ADA Group 2 units use separate wall oven + cooktop$0.20$0.00$0.201.00
Stove / OvenPath 2Same as Path 1$0.20$0.00$0.201.00
Stove / OvenPath 3Same as Path 1$0.20$0.00$0.201.00

Path Comparison - Electrical

ItemPathDetailed SpecificationsCost $/sfIncentive $/sfNet $/sfOpEx Factor
LightingPath 1100% LED$0.20$0.00$0.200.85
LightingPath 2Same as Path 1$0.20$0.00$0.200.85
LightingPath 3Same as Path 1$0.20$0.00$0.200.85
Solar ReadyPath 1Designated Solar Zone: Reserve a contiguous area equal to at least 40% of the total horizontal roof area. Zone free of obstructions, minimum 5 ft wide. 5 PSF collateral dead load. Conduit pathways and reserved breaker space.$0.05$0.00$0.051.00
Solar ReadyPath 2Same as Path 1$0.05$0.00$0.051.00
Solar ReadyPath 3Same as Path 1$0.05$0.00$0.051.00
EV ReadyPath 1EV Ready infrastructure for at least 20% of total parking. Branch circuit and termination for required spaces, rated for at least 6.2 kVA per space.$0.30$0.00$0.301.00
EV ReadyPath 2Same as Path 1$0.30$0.00$0.301.00
EV ReadyPath 3Same as Path 1$0.30$0.00$0.301.00

Path Comparison - Soft Costs

ItemPathDetailed SpecificationsCost $/sfIncentive $/sfNet $/sfOpEx Factor
Paperwork & ModelingPath 1HERS/ERI energy model, 2021 IECC checklists, ENERGY STAR checklists, incentive documentation.$0.40$1.82-$1.421.00
Paperwork & ModelingPath 2HERS/ERI energy model, 2021 IECC checklists, ENERGY STAR checklists, incentive documentation.$0.40$1.82-$1.421.00
Paperwork & ModelingPath 3HERS/ERI energy model, 2021 IECC checklists, ENERGY STAR checklists, incentive documentation.$0.40$1.82-$1.421.00
Testing & VerificationPath 1Unit Blower Door Test, Mechanical Ventilation Testing, Room Balancing, Predrywall & Final Inspection.$0.30$0.00$0.301.00
Testing & VerificationPath 2Unit Blower Door Test, Mechanical Ventilation Testing, Room Balancing, Predrywall & Final Inspection.$0.30$0.00$0.301.00
Testing & VerificationPath 3Unit Blower Door Test, Mechanical Ventilation Testing, Room Balancing, Predrywall & Final Inspection.$0.30$0.00$0.301.00

Additional Design Considerations Not Represented In This Study

The following construction and equipment alternatives were evaluated during VE and ruled out for the reasons noted. These options remain available if project conditions change.

HPWH Removal (electric resistance UEF 0.95): A path swapping the heat pump water heater for an electric resistance storage tank at UEF 0.95 was modeled. The HPWH-to-electric-resistance swap costs 8 to 11 HERS points per unit (worst case modeled at HERS 52.85 versus baseline 42). Even with all available compensating measures applied (tighter air sealing, induction range, heat pump dryer, premium HVAC class), the path remained 5+ points over the HERS 45 target. The HPWH is essential to compliance for this project. Removing it would also forfeit the $132,500 MassSave HPWH adder. Path was eliminated as construction-blocked.

Drain Water Heat Recovery (DWHR): Not specified in the architect's plans and not requested by the client. Retrofitting DWHR requires specific vertical drain routing and pipe-in-pipe heat exchanger detailing that the design is not set up for. Per ECC policy, DWHR is not added speculatively to any path.

Induction Cooking: Worth approximately 0.3 HERS points per unit and adds $300-500 per unit installed cost versus standard electric coil cooktops. Not needed for any path to pass; held in reserve as a tightening lever if any unit type fails final Ekotrope verification in Phase 3.

Heat Pump Dryer: Worth approximately 0.4 HERS points per unit versus the specified Whirlpool electric vented dryer. Heat pump dryers run 8-15 dB louder and have a longer cycle time, which can drive tenant complaints in an apartment context. The standard vented dryer specified by the developer is appropriate for the building type. Not included in any path.

Triple-pane Windows on Path 2: The Intus Supera CW70 windows on Path B are the same product specified in the 50% Permit Set. They are passive-house grade (U-0.17, SHGC-0.32) and significantly exceed the HERS 45 compliance threshold. While a less aggressive triple-pane (U-0.20 to U-0.22) would also pass, the Intus product is already specified, integrated with the facade detail, and is part of the building's luxury positioning. No window change recommended on Path B.

Continuous Insulation Reduction (R-12.6 to lower): Tested partial reduction of CI (e.g., 2 inches mineral wool, R-8.4) but the cost savings are modest compared to the labor savings of eliminating Z-girt rainscreen entirely. Path B's full elimination of CI captures the larger cost lever.

Tighter Air Sealing (0.30 to 0.20 CFM50/sqft shell): Worth approximately 1.5 HERS points per unit. Not needed for any path to pass; held in reserve if as-built blower door tests come in soft.

HVAC Tier Bump (HSPF2 9 to HSPF2 11+): Premium ducted CCHP products at HSPF2 11+ (e.g., Carrier Infinity 38M, Mitsubishi PUZ inverter platforms) would add approximately $2,000-3,000 per unit and yield 1-2 HERS points. Not cost-effective unless required for a path that would otherwise fail. Daikin Aurora HSPF2 9.0 specified in the plans is sufficient.